Define Activities
Foundational concept
Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.
Define Activities is the process of identifying and documenting the specific actions to be performed to produce the project deliverables.
Know it well enough for the exam? Questions on Define Activities are scenario-based, not definitional.
Practice it freeExplanation
Define Activities takes the work packages from the work breakdown structure (WBS) and decomposes them further into schedule activities. While a work package is the lowest level of the WBS, it may still be too large to estimate or schedule directly. Activities represent the effort needed to complete each work package and are the smallest units of work in the schedule.
The primary inputs to this process are the project management plan (particularly the schedule management plan and scope baseline), enterprise environmental factors, and organizational process assets. The key tools and techniques include decomposition, rolling wave planning, and expert judgment. Rolling wave planning is especially useful when future work is not yet fully understood, allowing near-term activities to be defined in detail while future activities remain at a higher level.
The outputs of Define Activities are the activity list, activity attributes, milestone list, and change requests. These outputs feed directly into subsequent scheduling processes such as Sequence Activities and Estimate Activity Durations.
Key Points
- •Decomposes work packages from the WBS into schedule activities
- •Uses decomposition, rolling wave planning, and expert judgment
- •Produces the activity list, activity attributes, and milestone list
- •Activities are the smallest units of work that feed into the schedule
Exam Tip
Know the difference between a work package (lowest WBS element, defined in scope) and an activity (scheduling unit derived from a work package). Define Activities bridges scope and schedule.
Frequently Asked Questions
Related Topics
Activity List
The activity list is a comprehensive list of all schedule activities required on the project, including an activity identifier and a scope of work description for each activity.
Activity Attributes
Activity attributes are additional details associated with each schedule activity that extend the description beyond what is in the activity list.
Milestone List
A milestone list identifies all project milestones and indicates whether the milestone is mandatory (required by contract) or optional (based on project requirements or historical information).
Work Breakdown Structure (WBS)
A work breakdown structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Resource Smoothing
Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Part of
Schedule Management
Practice Define Activities
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.