Skip to content
PMPCAPM

Milestone List

A milestone list identifies all project milestones and indicates whether the milestone is mandatory (required by contract) or optional (based on project requirements or historical information).

Share:

Explanation

A milestone is a significant point or event in the project that has zero duration. Milestones do not consume resources or time; they mark the completion of a key deliverable, phase, or decision point. The milestone list is an output of the Define Activities process and catalogs all such points for the project.

Milestones can be mandatory or optional. Mandatory milestones are those required by contract, regulation, or organizational policy, such as a contractual delivery date or a regulatory approval checkpoint. Optional milestones are established by the project team based on historical information or project needs, such as the completion of a design review or the end of a testing phase.

The milestone list serves as an input to the Sequence Activities process and is commonly used in high-level schedule reporting. Milestone charts provide executives and stakeholders with a summary view of the project timeline without the detail of a full Gantt chart. Milestones are also used as checkpoints for go/no-go decisions during phase gate reviews.

Key Points

  • Milestones have zero duration and represent significant project events
  • Can be mandatory (contractual) or optional (team-selected)
  • Output of the Define Activities process
  • Used for high-level reporting and phase gate reviews

Exam Tip

Remember that milestones have zero duration. If an exam question describes a "milestone" with a duration, it is actually an activity, not a milestone.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Resource Smoothing

Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Part of

Schedule Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.