Milestone List
A milestone list identifies all project milestones and indicates whether the milestone is mandatory (required by contract) or optional (based on project requirements or historical information).
Know it well enough for the exam? Questions on Milestone List are scenario-based, not definitional.
Practice it freeExplanation
A milestone is a significant point or event in the project that has zero duration. Milestones do not consume resources or time; they mark the completion of a key deliverable, phase, or decision point. The milestone list is an output of the Define Activities process and catalogs all such points for the project.
Milestones can be mandatory or optional. Mandatory milestones are those required by contract, regulation, or organizational policy, such as a contractual delivery date or a regulatory approval checkpoint. Optional milestones are established by the project team based on historical information or project needs, such as the completion of a design review or the end of a testing phase.
The milestone list serves as an input to the Sequence Activities process and is commonly used in high-level schedule reporting. Milestone charts provide executives and stakeholders with a summary view of the project timeline without the detail of a full Gantt chart. Milestones are also used as checkpoints for go/no-go decisions during phase gate reviews.
Key Points
- •Milestones have zero duration and represent significant project events
- •Can be mandatory (contractual) or optional (team-selected)
- •Output of the Define Activities process
- •Used for high-level reporting and phase gate reviews
Exam Tip
Remember that milestones have zero duration. If an exam question describes a "milestone" with a duration, it is actually an activity, not a milestone.
Frequently Asked Questions
Related Topics
Define Activities
Define Activities is the process of identifying and documenting the specific actions to be performed to produce the project deliverables.
Milestone Chart
A milestone chart is a schedule presentation that identifies only the start or completion of major deliverables and key external interfaces, displaying milestones on a timeline.
Activity List
The activity list is a comprehensive list of all schedule activities required on the project, including an activity identifier and a scope of work description for each activity.
Schedule Baseline
The schedule baseline is the approved version of the schedule model that is used as a basis for comparison with actual results to determine if corrective or preventive action is needed.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Resource Smoothing
Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Part of
Schedule Management
Practice Milestone List
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.