Skip to content
PMPCAPM

Avoid (Risk Strategy)

Avoid is a threat response strategy that eliminates the threat by changing the project management plan to remove the risk entirely, protect the project objectives, or relax the objective that is at risk.

Share:

Explanation

The avoid strategy takes action to ensure the threat cannot occur or that it can have no impact on the project. This might involve changing the project scope, adjusting the schedule, modifying the technical approach, or using a proven technology instead of an unproven one.

For example, if a complex integration poses a risk of significant delays, the team might avoid the risk by removing that integration from scope or by selecting a different technology with a proven track record. Extending the project schedule to allow more testing time is another form of avoidance if it removes the schedule risk.

Avoidance is the most definitive threat response but may not always be practical or cost-effective. It often involves trade-offs—removing scope may reduce risk but also reduces delivered value. The strategy is typically reserved for high-priority threats where the cost of avoidance is justified by the severity of the potential impact.

Key Points

  • Eliminates the threat entirely by changing the project plan
  • May involve scope changes, schedule extensions, or technology substitutions
  • Most definitive response but may involve trade-offs in scope or cost
  • Best suited for high-priority threats where avoidance cost is justified

Exam Tip

Avoid means the risk is completely eliminated. If the risk still exists at a reduced level, that is mitigation, not avoidance.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Transfer (Risk Strategy)

Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Part of

Risk Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.