Skip to content
PMPCAPM

Avoid (Risk Strategy)

Avoid is a threat response strategy that eliminates the threat by changing the project management plan to remove the risk entirely, protect the project objectives, or relax the objective that is at risk.

Share:

Know it well enough for the exam? Questions on Avoid (Risk Strategy) are scenario-based, not definitional.

Practice it free

Explanation

The avoid strategy takes action to ensure the threat cannot occur or that it can have no impact on the project. This might involve changing the project scope, adjusting the schedule, modifying the technical approach, or using a proven technology instead of an unproven one.

For example, if a complex integration poses a risk of significant delays, the team might avoid the risk by removing that integration from scope or by selecting a different technology with a proven track record. Extending the project schedule to allow more testing time is another form of avoidance if it removes the schedule risk.

Avoidance is the most definitive threat response but may not always be practical or cost-effective. It often involves trade-offs—removing scope may reduce risk but also reduces delivered value. The strategy is typically reserved for high-priority threats where the cost of avoidance is justified by the severity of the potential impact.

Key Points

  • •Eliminates the threat entirely by changing the project plan
  • •May involve scope changes, schedule extensions, or technology substitutions
  • •Most definitive response but may involve trade-offs in scope or cost
  • •Best suited for high-priority threats where avoidance cost is justified

Exam Tip

Avoid means the risk is completely eliminated. If the risk still exists at a reduced level, that is mitigation, not avoidance.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Transfer (Risk Strategy)

Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Part of

Risk Management

Study full domain →

Practice Avoid (Risk Strategy)

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.