Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Share:

Know it well enough for the exam? Questions on Schedule Performance Index (SPI) are scenario-based, not definitional.

Practice it free

Explanation

The Schedule Performance Index measures how efficiently the project team is using its time. An SPI of 1.0 means the project is exactly on schedule. An SPI greater than 1.0 means the project is ahead of schedule, and an SPI less than 1.0 means the project is behind schedule.

The formula is SPI = EV / PV. For example, if EV = $40,000 and PV = $50,000, then SPI = 0.80, meaning the project is only accomplishing 80% of the planned work per unit of time. The project is progressing at 80% of its planned rate.

Like SV, SPI converges to 1.0 at project completion because all planned value will have been earned. SPI is used throughout the project to track schedule trends and is also used in some EAC formulas to forecast final project costs when schedule performance affects cost outcomes.

Key Points

  • •Formula: SPI = EV / PV
  • •SPI > 1.0 = ahead of schedule; SPI < 1.0 = behind schedule
  • •Converges to 1.0 at project completion
  • •Used in some EAC forecasting formulas

Exam Tip

SPI = EV / PV. Greater than 1.0 is good. An SPI of 0.8 means you are accomplishing only 80 cents of work for every dollar of planned work at this point.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Power/Influence Grid

The power/influence grid is a stakeholder classification model that groups stakeholders based on their level of authority (power) and their active involvement or ability to affect the project (influence).

Predictive Life Cycle (Waterfall)

A predictive life cycle is a plan-driven approach where the project scope, schedule, and cost are determined early and changes are carefully managed.

Part of

Cost Management

Study full domain →

Practice Schedule Performance Index (SPI)

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.