Skip to content
PMPCAPM

Project Documents

Project documents are the collection of documents used to manage a project that are not part of the project management plan. They include logs, registers, reports, and other records that support project execution.

Share:

Know it well enough for the exam? Questions on Project Documents are scenario-based, not definitional.

Practice it free

Explanation

The PMBOK Guide distinguishes between three categories of project documentation: the project management plan (which defines how the project is managed), project documents (which support execution and decision-making), and business documents (which justify the project from a business perspective). Project documents are numerous and varied, and they evolve throughout the project lifecycle.

Common project documents include the activity list, assumption log, basis of estimates, change log, cost estimates, duration estimates, issue log, lessons learned register, milestone list, quality reports, requirements documentation, requirements traceability matrix, resource breakdown structure, risk register, risk report, schedule data, stakeholder register, and team charter. Each serves a specific purpose in supporting one or more project management processes.

Project documents are inputs and outputs to processes across all knowledge areas. They are updated frequently as the project progresses. While they are not formally controlled to the same degree as the project management plan baselines, they should still be managed and version-controlled to ensure consistency and accuracy. At project closure, project documents are archived as organizational process assets for future reference.

Key Points

  • •Support documents that are NOT part of the project management plan
  • •Include logs, registers, estimates, reports, and other records
  • •Updated frequently throughout the project lifecycle
  • •Archived as organizational process assets at project closure

Exam Tip

Know the difference: the project management plan defines how the project is managed (including baselines and subsidiary plans). Project documents support the plan but are separate from it. The exam tests this classification.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Change Control Board (CCB)

A Change Control Board (CCB) is a formally chartered group responsible for reviewing, evaluating, approving, deferring, or rejecting changes to the project, and for recording and communicating those decisions.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Part of

Integration Management

Study full domain →

Practice Project Documents

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.