Skip to content
PMPCAPM

Close Project or Phase

Foundational concept

Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.

Close Project or Phase is the process of finalizing all activities for the project, phase, or contract, including archiving project information, releasing resources, and completing final deliverable acceptance.

Share:

Know it well enough for the exam? Questions on Close Project or Phase are scenario-based, not definitional.

Practice it free

Explanation

This process ensures that all project work is completed, objectives are met, and the project is formally closed. It involves verifying that all deliverables have been accepted, ensuring all financial transactions are completed, transferring the final product to the customer or operations, collecting final lessons learned, archiving project records, and releasing project resources.

Key inputs include the project charter, project management plan, project documents (such as the assumption log, lessons learned register, milestone list, and risk register), accepted deliverables, business documents, agreements, procurement documentation, and organizational process assets. Tools and techniques include expert judgment, data analysis (document analysis, regression analysis, trend analysis, variance analysis), and meetings.

Outputs include the final product, service, or result transition, a final report, updates to organizational process assets (such as the lessons learned repository and historical information), and updates to project documents. The final report summarizes the project performance. Even when a project is terminated early — whether due to cancellation, resource constraints, or other reasons — the close process should still be performed to capture lessons learned and formally release resources.

Key Points

  • •Ensures formal acceptance of deliverables and releases all project resources
  • •Final lessons learned are collected and transferred to the lessons learned repository
  • •Must be performed even if the project is terminated early or cancelled
  • •Produces a final report summarizing project performance against baselines

Exam Tip

The exam may test whether you know that Close Project or Phase must happen even on cancelled projects. Always close formally to capture lessons learned and release resources.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Change Control Board (CCB)

A Change Control Board (CCB) is a formally chartered group responsible for reviewing, evaluating, approving, deferring, or rejecting changes to the project, and for recording and communicating those decisions.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Part of

Integration Management

Study full domain →

Practice Close Project or Phase

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.