Skip to content
PMPCAPM

Perform Integrated Change Control

Foundational concept

Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.

Perform Integrated Change Control is the process of reviewing all change requests, approving or rejecting changes, managing changes to deliverables, project documents, and the project management plan, and communicating the decisions.

Share:

Know it well enough for the exam? Questions on Perform Integrated Change Control are scenario-based, not definitional.

Practice it free

Explanation

This process is the gatekeeper for all project changes and is performed from project inception through completion. It ensures that every change is evaluated holistically — considering the impact on scope, schedule, cost, quality, resources, and risk — before a decision is made. The project manager is responsible for managing this process, though a Change Control Board (CCB) may be established to review and make decisions on change requests.

Key inputs include the project management plan (especially the change management plan and configuration management plan), project documents (such as the basis of estimates and the requirements traceability matrix), work performance reports, change requests, enterprise environmental factors, and organizational process assets. Tools and techniques include expert judgment, change control tools, data analysis (alternatives analysis, cost-benefit analysis), decision making (voting, autocratic, multicriteria), and meetings.

Outputs include approved change requests, updates to the project management plan, and updates to project documents. Approved change requests are then implemented through the Direct and Manage Project Work process. All change requests and their dispositions must be recorded in the change log. Configuration management activities ensure that the description and status of project deliverables are accurate and complete.

Key Points

  • •Central gatekeeper process for all project changes — nothing changes without going through it
  • •Evaluates the holistic impact of changes across all project constraints
  • •The CCB may approve or reject changes; the project manager manages the process
  • •Approved changes are implemented via Direct and Manage Project Work

Exam Tip

Every change request must go through Perform Integrated Change Control, regardless of size. The project manager cannot approve baseline changes unilaterally — that requires the CCB or sponsor, depending on organizational policy.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Change Control Board (CCB)

A Change Control Board (CCB) is a formally chartered group responsible for reviewing, evaluating, approving, deferring, or rejecting changes to the project, and for recording and communicating those decisions.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Part of

Integration Management

Study full domain →

Practice Perform Integrated Change Control

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.