Direct and Manage Project Work
Foundational concept
Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.
Direct and Manage Project Work is the process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the project objectives.
Know it well enough for the exam? Questions on Direct and Manage Project Work are scenario-based, not definitional.
Practice it freeExplanation
This process is where the majority of project resources and budget are expended. It takes place during the Executing process group and involves carrying out the activities defined in the project management plan to produce the project deliverables. The project manager coordinates all execution activities, manages technical and organizational interfaces, and ensures the team follows the plan.
Key inputs include the project management plan, project documents (such as the change log, lessons learned register, and risk register), approved change requests, enterprise environmental factors, and organizational process assets. Tools and techniques include expert judgment, the project management information system (PMIS), and meetings.
Important outputs of this process include deliverables, work performance data, issue log updates, change requests, and updates to the project management plan and project documents. Work performance data is raw, unanalyzed data collected during execution — such as percentage of work completed, start and finish dates, and number of defects — which later feeds into monitoring and controlling processes for analysis.
Key Points
- •Core executing process where deliverables are produced and most budget is spent
- •Implements approved change requests alongside planned project work
- •Produces work performance data — the raw observations and measurements from execution
- •Change requests can emerge from this process when issues or improvements are identified
Exam Tip
Know the difference between work performance data (raw, from Executing), work performance information (analyzed, from Monitoring & Controlling), and work performance reports (formatted, for communication).
Frequently Asked Questions
Related Topics
Project Management Plan
The project management plan is the document that describes how the project will be executed, monitored and controlled, and closed.
Perform Integrated Change Control
Perform Integrated Change Control is the process of reviewing all change requests, approving or rejecting changes, managing changes to deliverables, project documents, and the project management plan, and communicating the decisions.
Change Requests
A change request is a formal proposal to modify any document, deliverable, or baseline on a project. Change requests include corrective actions, preventive actions, defect repairs, and updates.
Project Management Information System (PMIS)
A Project Management Information System (PMIS) is an information system consisting of tools and techniques used to gather, integrate, and disseminate the outputs of project management processes.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Change Control Board (CCB)
A Change Control Board (CCB) is a formally chartered group responsible for reviewing, evaluating, approving, deferring, or rejecting changes to the project, and for recording and communicating those decisions.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Part of
Integration Management
Practice Direct and Manage Project Work
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.