Skip to content
PMPCAPM

Crashing

Crashing is a schedule compression technique in which additional resources are added to critical path activities to reduce their duration at the least additional cost.

Share:

Know it well enough for the exam? Questions on Crashing are scenario-based, not definitional.

Practice it free

Explanation

Crashing is one of two primary schedule compression techniques. It involves adding resources to activities on the critical path to reduce the project duration. Typical crashing strategies include assigning additional team members to an activity, authorizing overtime, paying for expedited delivery of materials, or using more experienced (and more expensive) resources.

The key principle of crashing is to achieve the maximum schedule compression for the minimum incremental cost. To do this, the project manager analyzes the critical path activities, determines the crash cost per unit of time saved for each activity, and then crashes the activities in order of lowest cost per unit of time saved. Crashing continues until the desired schedule reduction is achieved, no more crashing is possible, or the cost of further crashing exceeds the benefit.

Crashing does not always work. Some activities cannot be shortened by adding resources due to the nature of the work (for example, a task that requires sequential drying or curing time). Adding too many resources can also create diminishing returns or negative effects due to coordination overhead. Crashing always increases cost and may also introduce additional risk.

Key Points

  • •Adds resources to critical path activities to reduce duration
  • •Always increases project cost
  • •Applied to activities with the lowest crash cost per time unit saved first
  • •Not all activities can be effectively crashed

Exam Tip

On the exam, crash the critical path activity with the lowest crash cost per unit of time saved first. If the critical path changes after crashing, recalculate.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Resource Smoothing

Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Part of

Schedule Management

Study full domain →

Practice Crashing

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.