Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Share:

Know it well enough for the exam? Questions on Earned Value Management (EVM) are scenario-based, not definitional.

Practice it free

Explanation

Earned Value Management compares the amount of work that was planned with what was actually accomplished and the actual cost incurred. It requires three key data points: Planned Value (PV), Earned Value (EV), and Actual Cost (AC). From these three measurements, variances and performance indices are calculated.

EVM enables the project manager to answer critical questions: Are we ahead of or behind schedule? Are we over or under budget? How much will the project cost at completion? By comparing EV to PV, schedule performance is measured. By comparing EV to AC, cost performance is measured.

Key EVM metrics include Schedule Variance (SV = EV - PV), Cost Variance (CV = EV - AC), Schedule Performance Index (SPI = EV / PV), Cost Performance Index (CPI = EV / AC), Estimate at Completion (EAC), Estimate to Complete (ETC), Variance at Completion (VAC), and To-Complete Performance Index (TCPI). EVM provides early warning signals of performance problems and supports data-driven decision making.

Key Points

  • •Integrates scope, schedule, and cost measurement
  • •Three foundational values: PV, EV, and AC
  • •Calculates variances (SV, CV) and indices (SPI, CPI)
  • •Enables forecasting of final project cost and schedule

Exam Tip

EVM is heavily tested on both PMP and CAPM exams. Memorize all formulas and know how to interpret positive/negative variances and indices above/below 1.0.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Part of

Cost Management

Study full domain →

Practice Earned Value Management (EVM)

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.