Develop Project Charter
Foundational concept
Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.
Develop Project Charter is the process of creating the document that formally authorizes a project or phase and documents the initial requirements that satisfy stakeholder needs and expectations.
Know it well enough for the exam? Questions on Develop Project Charter are scenario-based, not definitional.
Practice it freeExplanation
Develop Project Charter is the first process in Integration Management and belongs to the Initiating process group. Its primary output is the project charter, which establishes a partnership between the performing organization and the requesting entity. The process uses inputs such as business documents (the business case and benefits management plan), agreements, enterprise environmental factors, and organizational process assets.
Key tools and techniques used in this process include expert judgment, data gathering (such as brainstorming, focus groups, and interviews), and interpersonal and team skills like conflict management and facilitation. Expert judgment is particularly important because it draws on specialized knowledge from subject matter experts, industry groups, consultants, and stakeholders to evaluate the inputs.
This process is performed once or at predefined points in the project. It ensures that the project has a sound basis and that the organization is committed to the investment. The project manager should be identified and assigned as early as possible, ideally before the charter is developed and always before planning begins.
Key Points
- •First process in Integration Management and the Initiating process group
- •Uses business documents, agreements, and organizational factors as key inputs
- •Expert judgment and data gathering are primary tools and techniques
- •Performed once or at predefined points to authorize the project or phase
Exam Tip
On the exam, know that the business case and benefits management plan are inputs to this process but are NOT outputs of it. They exist before the charter is created.
Frequently Asked Questions
Related Topics
Project Charter
A project charter is a document issued by the project sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Business Case
A business case is a documented economic feasibility study that establishes the validity of the benefits of a selected component lacking sufficient definition and that is used as a basis for the authorization of further project management activities.
Benefits Management Plan
A benefits management plan is a document that describes how and when the benefits of a project will be delivered and the mechanisms for measuring those benefits.
Expert Judgment
Expert judgment is a technique that relies on the specialized knowledge and experience of individuals or groups with training, expertise, or skills in a specific area relevant to the activity being performed.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Change Control Board (CCB)
A Change Control Board (CCB) is a formally chartered group responsible for reviewing, evaluating, approving, deferring, or rejecting changes to the project, and for recording and communicating those decisions.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Part of
Integration Management
Practice Develop Project Charter
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.