Skip to content
PMPCAPM

Business Case

A business case is a documented economic feasibility study that establishes the validity of the benefits of a selected component lacking sufficient definition and that is used as a basis for the authorization of further project management activities.

Share:

Know it well enough for the exam? Questions on Business Case are scenario-based, not definitional.

Start free

Explanation

The business case is a business document that provides the justification for undertaking a project. It presents the analysis of costs, benefits, risks, and alternatives that supports the decision to invest in the project. The business case is typically developed before the project is formally initiated and is an input to the Develop Project Charter process.

A comprehensive business case includes the business need or problem being addressed, the analysis of the situation (including root cause analysis), the recommended solution, an evaluation of alternatives considered, the expected costs and benefits (including financial metrics such as ROI, NPV, IRR, and payback period), risks and assumptions, success criteria, and the organizational strategy alignment.

The business case is owned by the project sponsor or the business, not the project manager. It remains relevant throughout the project and is periodically reviewed — particularly at phase gates — to confirm that the project still delivers value. If the business case is no longer valid (for example, due to market changes), the project may be cancelled. The business case is also referenced during project closure to assess whether the intended benefits are on track to be realized.

Key Points

  • •Business document that justifies the project investment
  • •Includes cost-benefit analysis, alternatives, risks, and strategic alignment
  • •Owned by the sponsor or business, not the project manager
  • •Reviewed at phase gates to confirm continued viability

Exam Tip

The business case is created BEFORE the project charter and is an input to Develop Project Charter. Know that it is a business document, not a project document or part of the project management plan.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Change Control Board (CCB)

A Change Control Board (CCB) is a formally chartered group responsible for reviewing, evaluating, approving, deferring, or rejecting changes to the project, and for recording and communicating those decisions.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Part of

Integration Management

Study full domain →

Practice Business Case

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.