Cost Management Plan
The cost management plan is a component of the project management plan that describes how project costs will be planned, structured, estimated, budgeted, and controlled.
Know it well enough for the exam? Questions on Cost Management Plan are scenario-based, not definitional.
Practice it freeExplanation
The cost management plan establishes the criteria and activities for developing, managing, and controlling the project budget. It documents the level of accuracy required for estimates, the units of measure to be used, organizational procedures and links, control thresholds, and rules for earned value measurement.
Key elements of the cost management plan include the level of precision (degree of rounding), level of accuracy (acceptable range for estimates), organizational procedures links (such as the WBS component used for cost accounting), control thresholds (variance amounts that trigger action), rules of performance measurement for EVM, and reporting formats and frequency.
The cost management plan may also establish the funding limit reconciliation approach, which addresses how expenditures will be reconciled with funding limits. This plan guides the project team through all cost-related decisions and activities.
Key Points
- •Component of the project management plan
- •Defines units of measure, level of precision, and level of accuracy
- •Establishes control thresholds for cost variance
- •Specifies EVM rules of performance measurement
Exam Tip
The cost management plan is a subsidiary plan within the project management plan. Know the difference between the plan itself and the outputs of the processes it governs.
Frequently Asked Questions
Related Topics
Plan Cost Management
Plan Cost Management is the process of defining how project costs will be estimated, budgeted, managed, monitored, and controlled.
Cost Baseline
The cost baseline is the approved version of the time-phased project budget, excluding management reserves, used as a reference for measuring and monitoring cost performance.
Project Budget
The project budget is the total authorized funds allocated for the project, composed of the cost baseline plus management reserves.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Cost Performance Index (CPI)
Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.
Schedule Performance Index (SPI)
Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.
Earned Value Management (EVM)
Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Part of
Cost Management
Practice Cost Management Plan
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.