Skip to content
PMPCAPM

Cost Management Plan

The cost management plan is a component of the project management plan that describes how project costs will be planned, structured, estimated, budgeted, and controlled.

Share:

Explanation

The cost management plan establishes the criteria and activities for developing, managing, and controlling the project budget. It documents the level of accuracy required for estimates, the units of measure to be used, organizational procedures and links, control thresholds, and rules for earned value measurement.

Key elements of the cost management plan include the level of precision (degree of rounding), level of accuracy (acceptable range for estimates), organizational procedures links (such as the WBS component used for cost accounting), control thresholds (variance amounts that trigger action), rules of performance measurement for EVM, and reporting formats and frequency.

The cost management plan may also establish the funding limit reconciliation approach, which addresses how expenditures will be reconciled with funding limits. This plan guides the project team through all cost-related decisions and activities.

Key Points

  • Component of the project management plan
  • Defines units of measure, level of precision, and level of accuracy
  • Establishes control thresholds for cost variance
  • Specifies EVM rules of performance measurement

Exam Tip

The cost management plan is a subsidiary plan within the project management plan. Know the difference between the plan itself and the outputs of the processes it governs.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Power/Influence Grid

The power/influence grid is a stakeholder classification model that groups stakeholders based on their level of authority (power) and their active involvement or ability to affect the project (influence).

Part of

Cost Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.