Team Charter
A team charter is a document that establishes the team values, agreements, and operating guidelines, including communication guidelines, decision-making criteria, conflict resolution processes, meeting guidelines, and team agreements.
Know it well enough for the exam? Questions on Team Charter are scenario-based, not definitional.
Practice it freeExplanation
The team charter is an output of the Plan Resource Management process and serves as a foundational document for how the team will work together. It is created early in the project and establishes expectations that reduce misunderstandings and conflict later. The charter is developed collaboratively by the team members, which builds buy-in and commitment.\n\nA well-crafted team charter typically includes ground rules for meetings, communication norms, decision-making approaches, conflict resolution methods, and working agreements. It may also cover how the team will handle disagreements, how members will support each other, and what behaviors are expected. In agile environments, these agreements are often called working agreements or team norms.\n\nThe team charter is distinct from the project charter. The project charter authorizes the project and defines its high-level scope, while the team charter focuses on how team members will interact and collaborate. Revisiting and updating the team charter periodically helps maintain team alignment as the project evolves.
Key Points
- •Output of Plan Resource Management
- •Establishes team values, ground rules, and operating guidelines
- •Developed collaboratively to build team buy-in
- •Covers communication, decision-making, and conflict resolution norms
Exam Tip
Do not confuse the team charter with the project charter. The project charter authorizes the project; the team charter defines how the team will work together.
Frequently Asked Questions
Related Topics
Plan Resource Management
Plan Resource Management is the process of defining how to estimate, acquire, manage, and use team and physical resources for a project.
Develop Team
Develop Team is the process of improving competencies, team member interaction, and the overall team environment to enhance project performance.
Conflict Management
Conflict management is the practice of identifying and handling conflicts in a timely, constructive manner to minimize negative impacts and leverage disagreement for improved outcomes.
Project Charter
A project charter is a document issued by the project sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Stakeholder Mapping
Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.
Part of
Resource Management
Practice Team Charter
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.