Start-to-Start (SS) Dependency
A Start-to-Start (SS) dependency is a logical relationship in which a successor activity cannot start until a predecessor activity has started.
Know it well enough for the exam? Questions on Start-to-Start (SS) Dependency are scenario-based, not definitional.
Practice it freeExplanation
Start-to-Start dependencies allow two activities to begin at the same time or with a controlled offset. The successor activity can only start once the predecessor has started, but they do not need to finish together. This type of relationship is useful when two activities can run in parallel but one depends on the other beginning first.
For example, a project might have a coding activity and a documentation activity with an SS relationship. Documentation can begin once coding starts (since the documentation team needs to see some code to document), but the two activities proceed independently after that point. An SS relationship with a lag might specify that documentation starts two days after coding begins.
SS dependencies are less common than FS dependencies but are valuable for modeling concurrent work streams. They are frequently combined with FF (Finish-to-Finish) dependencies to fully constrain the timing between parallel activities, ensuring they both start and finish in a coordinated manner.
Key Points
- •Successor cannot start until predecessor starts
- •Allows parallel execution of activities
- •Often combined with FF dependencies for full constraint
- •Commonly used with lags to offset start times
Exam Tip
SS does not mean both activities start at exactly the same time. It means the successor cannot start until the predecessor has started. A lag can offset the starts.
Frequently Asked Questions
Related Topics
Precedence Diagramming Method (PDM)
The Precedence Diagramming Method (PDM) is a technique used to construct a schedule model in which activities are represented by nodes and are graphically linked by logical relationships to show the sequence of activities.
Finish-to-Start (FS) Dependency
A Finish-to-Start (FS) dependency is a logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Finish-to-Finish (FF) Dependency
A Finish-to-Finish (FF) dependency is a logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Leads and Lags
A lead is the amount of time a successor activity can be advanced with respect to a predecessor activity. A lag is the amount of time a successor activity must be delayed with respect to a predecessor activity.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Resource Smoothing
Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Part of
Schedule Management
Practice Start-to-Start (SS) Dependency
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.