Skip to content
PMPCAPM

Start-to-Start (SS) Dependency

A Start-to-Start (SS) dependency is a logical relationship in which a successor activity cannot start until a predecessor activity has started.

Share:

Explanation

Start-to-Start dependencies allow two activities to begin at the same time or with a controlled offset. The successor activity can only start once the predecessor has started, but they do not need to finish together. This type of relationship is useful when two activities can run in parallel but one depends on the other beginning first.

For example, a project might have a coding activity and a documentation activity with an SS relationship. Documentation can begin once coding starts (since the documentation team needs to see some code to document), but the two activities proceed independently after that point. An SS relationship with a lag might specify that documentation starts two days after coding begins.

SS dependencies are less common than FS dependencies but are valuable for modeling concurrent work streams. They are frequently combined with FF (Finish-to-Finish) dependencies to fully constrain the timing between parallel activities, ensuring they both start and finish in a coordinated manner.

Key Points

  • Successor cannot start until predecessor starts
  • Allows parallel execution of activities
  • Often combined with FF dependencies for full constraint
  • Commonly used with lags to offset start times

Exam Tip

SS does not mean both activities start at exactly the same time. It means the successor cannot start until the predecessor has started. A lag can offset the starts.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Resource Smoothing

Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Part of

Schedule Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.