Skip to content
PMPCAPM

Internal Rate of Return (IRR)

The internal rate of return (IRR) is the discount rate at which the net present value of all cash flows from a project equals zero, representing the project's expected annualized rate of return.

Share:

Explanation

IRR answers the question: what rate of return does this project earn? It is the discount rate that makes the present value of future cash inflows exactly equal to the initial investment. If the IRR exceeds the organization's required rate of return (hurdle rate), the project is considered financially attractive.

IRR is useful because it expresses a project's return as a percentage, making it easy to compare against the cost of capital or alternative investments. However, IRR has limitations: it assumes cash flows are reinvested at the IRR itself (which may be unrealistic), and it can produce multiple values for projects with alternating positive and negative cash flows.

On the exam, remember that higher IRR is generally better and that a project's IRR should exceed the organization's hurdle rate. You will not need to calculate IRR, but you must understand how to interpret and compare it.

Key Points

  • The discount rate at which NPV equals zero
  • Higher IRR is generally preferred
  • Should exceed the organization's hurdle rate to be viable
  • Expressed as a percentage, making comparisons intuitive

Exam Tip

Select the project with the higher IRR when comparing alternatives. If IRR is below the hurdle rate, the project does not meet the minimum required return.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Power/Influence Grid

The power/influence grid is a stakeholder classification model that groups stakeholders based on their level of authority (power) and their active involvement or ability to affect the project (influence).

Part of

Business Environment & Strategy

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.