Internal Rate of Return (IRR)
The internal rate of return (IRR) is the discount rate at which the net present value of all cash flows from a project equals zero, representing the project's expected annualized rate of return.
Know it well enough for the exam? Questions on Internal Rate of Return (IRR) are scenario-based, not definitional.
Practice it freeExplanation
IRR answers the question: what rate of return does this project earn? It is the discount rate that makes the present value of future cash inflows exactly equal to the initial investment. If the IRR exceeds the organization's required rate of return (hurdle rate), the project is considered financially attractive.
IRR is useful because it expresses a project's return as a percentage, making it easy to compare against the cost of capital or alternative investments. However, IRR has limitations: it assumes cash flows are reinvested at the IRR itself (which may be unrealistic), and it can produce multiple values for projects with alternating positive and negative cash flows.
On the exam, remember that higher IRR is generally better and that a project's IRR should exceed the organization's hurdle rate. You will not need to calculate IRR, but you must understand how to interpret and compare it.
Key Points
- •The discount rate at which NPV equals zero
- •Higher IRR is generally preferred
- •Should exceed the organization's hurdle rate to be viable
- •Expressed as a percentage, making comparisons intuitive
Exam Tip
Select the project with the higher IRR when comparing alternatives. If IRR is below the hurdle rate, the project does not meet the minimum required return.
Frequently Asked Questions
Related Topics
Net Present Value (NPV)
Net present value (NPV) is the difference between the present value of cash inflows and the present value of cash outflows over a period of time, used to assess the profitability of a project or investment.
Return on Investment (ROI)
Return on investment (ROI) is a financial metric that measures the percentage gain or loss generated by an investment relative to its cost, calculated as (Net Profit / Cost of Investment) x 100.
Project Selection Methods
Project selection methods are the techniques organizations use to evaluate and choose which projects to pursue, including mathematical models (NPV, IRR, BCR) and comparative approaches (scoring models, peer review).
Benefit-Cost Ratio (BCR)
The benefit-cost ratio (BCR) is a financial metric that compares the present value of benefits to the present value of costs, expressed as a ratio, to determine whether a project's benefits outweigh its costs.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Stakeholder Mapping
Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.
Part of
Business Environment & Strategy
Practice Internal Rate of Return (IRR)
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.