Skip to content
PMPCAPM

Benefit-Cost Ratio (BCR)

The benefit-cost ratio (BCR) is a financial metric that compares the present value of benefits to the present value of costs, expressed as a ratio, to determine whether a project's benefits outweigh its costs.

Share:

Know it well enough for the exam? Questions on Benefit-Cost Ratio (BCR) are scenario-based, not definitional.

Practice it free

Explanation

BCR provides a simple ratio to assess project viability. A BCR greater than 1.0 means benefits exceed costs—the project is worth pursuing. A BCR less than 1.0 means costs exceed benefits. A BCR of exactly 1.0 means benefits and costs are equal, providing no net gain.

To calculate BCR, divide the present value of all expected benefits by the present value of all expected costs. For example, if a project's benefits have a present value of $500,000 and its costs have a present value of $400,000, the BCR is 1.25. This means the project returns $1.25 for every $1.00 invested.

On the exam, BCR is one of the most commonly tested project selection metrics. When comparing multiple projects, select the one with the highest BCR (assuming all are above 1.0). BCR is particularly useful because it accounts for the time value of money when present values are used in the calculation.

Key Points

  • •BCR greater than 1.0 indicates benefits exceed costs
  • •Higher BCR is preferred when comparing projects
  • •Calculated as Present Value of Benefits / Present Value of Costs
  • •A BCR of less than 1.0 means the project should be rejected

Exam Tip

BCR > 1 means the project is viable. When comparing projects, choose the one with the highest BCR. This is one of the most commonly tested selection criteria.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Part of

Business Environment & Strategy

Study full domain →

Practice Benefit-Cost Ratio (BCR)

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.