Net Present Value (NPV)
Net present value (NPV) is the difference between the present value of cash inflows and the present value of cash outflows over a period of time, used to assess the profitability of a project or investment.
Know it well enough for the exam? Questions on Net Present Value (NPV) are scenario-based, not definitional.
Practice it freeExplanation
NPV accounts for the time value of money—the principle that a dollar today is worth more than a dollar in the future. By discounting all future cash flows back to present value using a chosen discount rate, NPV provides a single number that represents the net economic value of a project in today's terms.
A positive NPV means the project is expected to generate more value than it costs, making it a worthwhile investment. A negative NPV means the project's costs exceed its expected returns. When comparing multiple projects, the one with the highest NPV is generally the best financial choice, assuming similar risk profiles.
The discount rate used in NPV calculations reflects the organization's cost of capital or required rate of return. On the exam, you are unlikely to perform a full NPV calculation, but you must understand the concept and know that higher NPV is better and positive NPV indicates a viable investment.
Key Points
- •Accounts for the time value of money
- •Positive NPV means the project adds value; negative NPV means it does not
- •Higher NPV is preferred when comparing projects
- •Uses a discount rate reflecting the organization's cost of capital
Exam Tip
When choosing between projects, select the one with the highest positive NPV. A project with a negative NPV should generally be rejected.
Frequently Asked Questions
Related Topics
Internal Rate of Return (IRR)
The internal rate of return (IRR) is the discount rate at which the net present value of all cash flows from a project equals zero, representing the project's expected annualized rate of return.
Return on Investment (ROI)
Return on investment (ROI) is a financial metric that measures the percentage gain or loss generated by an investment relative to its cost, calculated as (Net Profit / Cost of Investment) x 100.
Payback Period
The payback period is the length of time required for an investment to recover its initial cost from the net cash inflows it generates.
Benefit-Cost Ratio (BCR)
The benefit-cost ratio (BCR) is a financial metric that compares the present value of benefits to the present value of costs, expressed as a ratio, to determine whether a project's benefits outweigh its costs.
Project Selection Methods
Project selection methods are the techniques organizations use to evaluate and choose which projects to pursue, including mathematical models (NPV, IRR, BCR) and comparative approaches (scoring models, peer review).
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Stakeholder Mapping
Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.
Part of
Business Environment & Strategy
Practice Net Present Value (NPV)
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.