Honesty (Ethical Principle)
Honesty is the PMI ethical principle requiring practitioners to understand the truth and act in a truthful manner, both in communications and in conduct.
Know it well enough for the exam? Questions on Honesty (Ethical Principle) are scenario-based, not definitional.
Practice it freeExplanation
The honesty value in the PMI Code of Ethics establishes that project managers must be truthful in all professional communications and create an environment where others feel safe to be truthful. This applies to status reports, stakeholder communications, estimates, risk assessments, and all other project information.
Aspirational standards encourage practitioners to earnestly seek to understand the truth, be truthful in communications and conduct, and create an environment where others feel safe to tell the truth. Mandatory standards prohibit engaging in or condoning dishonest behavior, including making misleading or false statements, stating half-truths, or providing information out of context with the intent to mislead.
On the exam, honesty questions often present a scenario where a project manager is pressured to present overly optimistic status reports or hide bad news from stakeholders or sponsors. The ethical answer always involves transparent and accurate reporting, even when the truth is uncomfortable.
Key Points
- •Understand the truth and act truthfully in all communications
- •Do not engage in or condone deceptive behavior
- •Create an environment where others feel safe to tell the truth
- •Never provide information out of context with intent to mislead
Exam Tip
When pressured by a sponsor or executive to present an optimistic project status that does not reflect reality, the honest response is to report the actual status and offer a plan to address the issues.
Frequently Asked Questions
Related Topics
PMI Code of Ethics and Professional Conduct
The PMI Code of Ethics and Professional Conduct is a foundational document that establishes the ethical expectations and behavioral standards for all PMI members, volunteers, and certification holders.
Truthful Reporting
Truthful reporting is the ethical obligation to provide accurate, complete, and timely information about project status, performance, risks, and issues to all authorized stakeholders.
Responsibility (Ethical Principle)
Responsibility is the PMI ethical principle requiring practitioners to take ownership of decisions, actions, and their consequences, and to act in the best interests of society, public safety, and the environment.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Stakeholder Mapping
Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.
Part of
Ethics & Professional Responsibility
Practice Honesty (Ethical Principle)
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.