Skip to content
PMPCAPM

Conduct Procurements

Foundational concept

Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.

Conduct Procurements is the process of obtaining seller responses, selecting a seller, and awarding a contract.

Share:

Know it well enough for the exam? Questions on Conduct Procurements are scenario-based, not definitional.

Practice it free

Explanation

Conduct Procurements bridges the gap between procurement planning and actual contract execution. During this process, the project team sends bid documents to potential sellers, receives proposals or bids, applies source selection criteria to evaluate responses, and negotiates with one or more sellers before awarding a contract.

Key tools and techniques include advertising to broaden the pool of potential sellers, bidder conferences to ensure all prospective sellers have a clear understanding of the procurement requirements, proposal evaluation techniques, and negotiation. In some organizations, a separate procurement or purchasing department handles this process.

The primary outputs are selected sellers, agreements (contracts), change requests, and updates to the project management plan and project documents. The contract becomes the legally binding agreement that governs the buyer-seller relationship for the duration of the procurement.

Key Points

  • •Belongs to the Executing process group
  • •Involves obtaining proposals, evaluating sellers, and awarding contracts
  • •Uses bidder conferences and proposal evaluation techniques
  • •Produces agreements (contracts) and selected sellers as outputs

Exam Tip

Conduct Procurements is in the Executing process group. A common exam trap is confusing it with Plan Procurement Management (Planning) or Control Procurements (Monitoring & Controlling).

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Part of

Procurement Management

Study full domain →

Practice Conduct Procurements

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.