Skip to content
CAPM

CAPM Exam Format and Structure

The CAPM exam consists of 150 multiple-choice questions to be completed in three hours, delivered at a Pearson VUE test center or via online proctored testing.

Share:

Know it well enough for the exam? Questions on CAPM Exam Format and Structure are scenario-based, not definitional.

Practice it free

Explanation

The CAPM exam contains 150 questions, of which 135 are scored and 15 are pretest (unscored) questions used by PMI for future exam development. You will not know which questions are pretest, so you must treat every question as if it counts. The total exam duration is three hours with no scheduled breaks.

Questions are distributed across four domains with approximate weightings: Project Management Fundamentals and Core Concepts (36%), Predictive Plan-Based Methodologies (17%), Agile Frameworks and Methodologies (20%), and Business Analysis Frameworks (27%). This means business analysis and project management fundamentals together account for nearly two-thirds of the exam.

The exam is available year-round at Pearson VUE testing centers worldwide and through online proctored testing from your home or office. Results are provided immediately upon completion, showing an overall pass or did-not-pass result along with performance by domain. PMI uses a psychometric analysis to determine the passing score, which is not publicly disclosed as a fixed percentage.

Key Points

  • •One hundred fifty questions total, with 135 scored and 15 unscored pretest questions
  • •Three-hour time limit with no scheduled breaks
  • •Four domains weighted as: Fundamentals (36%), Predictive (17%), Agile (20%), Business Analysis (27%)
  • •Available at Pearson VUE test centers or via online proctored testing

Exam Tip

You have just over one minute per question on average. Do not spend more than two minutes on any single question; flag it and return to it later.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Part of

CAPM-Specific Concepts

Study full domain →

Practice CAPM Exam Format and Structure

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.