Skip to content
PMPCAPM

Analogous Estimating

Analogous estimating uses historical data from similar past activities or projects as the basis for estimating the duration or cost of a current activity or project.

Share:

Explanation

Analogous estimating, also called top-down estimating, leverages the actual durations or costs from previous similar projects or activities to estimate the current one. It relies on expert judgment to adjust historical values based on known differences between the past and current situations, such as complexity, size, team experience, and environmental conditions.

This technique is most useful early in the project when limited detail is available about the current work. It is relatively quick and inexpensive to perform compared to more detailed techniques like bottom-up estimating. However, it is also less accurate because it depends on the degree of similarity between the current project and historical projects, as well as the quality of the expert judgment applied.

Analogous estimating works best when the past activities are substantially similar in nature (not just appearance), the estimators have the needed expertise, and the historical data is reliable. It can be applied at the project level (estimating total project duration based on similar projects) or at the activity level (estimating individual activity durations based on similar past activities).

Key Points

  • Also called top-down estimating
  • Uses historical data from similar past activities or projects
  • Quick and inexpensive but less accurate than detailed methods
  • Most useful early in the project when detail is limited

Exam Tip

Analogous estimating is a form of expert judgment using historical data. It is less costly but less accurate than bottom-up estimating.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Resource Smoothing

Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Part of

Schedule Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.