Skip to content
PMPCAPM

Analogous Estimating

Analogous estimating uses historical data from similar past activities or projects as the basis for estimating the duration or cost of a current activity or project.

Share:

Know it well enough for the exam? Questions on Analogous Estimating are scenario-based, not definitional.

Practice it free

Explanation

Analogous estimating, also called top-down estimating, leverages the actual durations or costs from previous similar projects or activities to estimate the current one. It relies on expert judgment to adjust historical values based on known differences between the past and current situations, such as complexity, size, team experience, and environmental conditions.

This technique is most useful early in the project when limited detail is available about the current work. It is relatively quick and inexpensive to perform compared to more detailed techniques like bottom-up estimating. However, it is also less accurate because it depends on the degree of similarity between the current project and historical projects, as well as the quality of the expert judgment applied.

Analogous estimating works best when the past activities are substantially similar in nature (not just appearance), the estimators have the needed expertise, and the historical data is reliable. It can be applied at the project level (estimating total project duration based on similar projects) or at the activity level (estimating individual activity durations based on similar past activities).

Key Points

  • •Also called top-down estimating
  • •Uses historical data from similar past activities or projects
  • •Quick and inexpensive but less accurate than detailed methods
  • •Most useful early in the project when detail is limited

Exam Tip

Analogous estimating is a form of expert judgment using historical data. It is less costly but less accurate than bottom-up estimating.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Resource Smoothing

Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Part of

Schedule Management

Study full domain →

Practice Analogous Estimating

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.