Acquire Resources

Foundational concept

Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.

Acquire Resources is the process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.

Share:

Know it well enough for the exam? Questions on Acquire Resources are scenario-based, not definitional.

Start free

Explanation

This process confirms resource availability and obtains the resources needed to complete project activities. Resources may be acquired from internal or external sources. The project management team may or may not have direct control over resource selection due to collective bargaining agreements, use of subcontractor personnel, matrix project environments, or other constraints.\n\nKey tools and techniques include decision-making (such as multi-criteria decision analysis), interpersonal and team skills (particularly negotiation), pre-assignment, and virtual teams. The project manager should effectively negotiate with functional managers, other project management teams, or external organizations to acquire appropriate resources.\n\nOutputs include physical resource assignments, project team assignments, resource calendars, change requests, and updates to the project management plan and project documents. This process is performed periodically throughout the project as resource needs evolve.

Key Points

  • •Confirms availability and obtains resources for project work
  • •Uses negotiation, pre-assignment, and multi-criteria decision analysis
  • •Resources may come from internal or external sources
  • •Performed periodically as resource needs change throughout the project

Exam Tip

In a matrix organization, the project manager must negotiate with functional managers to acquire team members. Remember that functional managers often have the final authority over resource assignment.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Part of

Resource Management

Study full domain →

Practice Acquire Resources

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.