Acquire Resources
Foundational concept
Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.
Acquire Resources is the process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.
Know it well enough for the exam? Questions on Acquire Resources are scenario-based, not definitional.
Start freeExplanation
This process confirms resource availability and obtains the resources needed to complete project activities. Resources may be acquired from internal or external sources. The project management team may or may not have direct control over resource selection due to collective bargaining agreements, use of subcontractor personnel, matrix project environments, or other constraints.\n\nKey tools and techniques include decision-making (such as multi-criteria decision analysis), interpersonal and team skills (particularly negotiation), pre-assignment, and virtual teams. The project manager should effectively negotiate with functional managers, other project management teams, or external organizations to acquire appropriate resources.\n\nOutputs include physical resource assignments, project team assignments, resource calendars, change requests, and updates to the project management plan and project documents. This process is performed periodically throughout the project as resource needs evolve.
Key Points
- •Confirms availability and obtains resources for project work
- •Uses negotiation, pre-assignment, and multi-criteria decision analysis
- •Resources may come from internal or external sources
- •Performed periodically as resource needs change throughout the project
Exam Tip
In a matrix organization, the project manager must negotiate with functional managers to acquire team members. Remember that functional managers often have the final authority over resource assignment.
Frequently Asked Questions
Related Topics
Negotiation (for Resources)
Negotiation for resources is the process by which the project manager discusses and agrees upon resource assignments with functional managers, other project teams, or external organizations to obtain the needed team members and physical resources.
Pre-Assignment
Pre-assignment is the practice of assigning specific team members to a project before resource planning is complete, often because they were promised in the project charter, proposal, or contract.
Virtual Teams
Virtual teams are groups of people with a shared goal who fulfill their roles with little or no face-to-face interaction, relying on communication technology to collaborate.
Multi-Criteria Decision Analysis
Multi-criteria decision analysis is a technique that uses a decision matrix to provide a systematic approach for evaluating candidates or options against a set of weighted criteria to make objective selection decisions.
Develop Team
Develop Team is the process of improving competencies, team member interaction, and the overall team environment to enhance project performance.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Stakeholder Mapping
Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.
Part of
Resource Management
Practice Acquire Resources
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.