Wideband Delphi
Wideband Delphi is a consensus-based estimation technique that extends the Delphi method by adding team discussion between anonymous estimation rounds to improve estimate accuracy.
Know it well enough for the exam? Questions on Wideband Delphi are scenario-based, not definitional.
Practice it freeExplanation
Wideband Delphi is a variation of the traditional Delphi technique adapted for software and project estimation. Like the original Delphi, it uses multiple rounds of anonymous estimation. However, Wideband Delphi adds group discussion between rounds, allowing estimators to share their reasoning, ask clarifying questions, and understand different perspectives before re-estimating.
The process typically involves a moderator presenting the work item, the team independently recording their estimates, all estimates being revealed simultaneously, the team discussing the highest and lowest estimates to understand the reasoning, and then re-estimating. This cycle continues until the estimates converge within an acceptable range.
Planning poker, widely used in agile teams, is a direct descendant of Wideband Delphi. Both techniques combine the bias-reduction benefits of anonymous estimation with the information-sharing benefits of team discussion. Wideband Delphi produces more accurate estimates than either individual expert judgment or simple group averaging.
Key Points
- •Extends Delphi with team discussion between anonymous estimation rounds
- •Reduces bias while sharing information that improves accuracy
- •Planning poker is a popular variant used in agile
- •Produces more accurate estimates than individual judgment or simple averaging
Exam Tip
Wideband Delphi differs from classic Delphi by adding face-to-face discussion between rounds. Planning poker is essentially Wideband Delphi adapted for agile teams.
Frequently Asked Questions
Related Topics
Delphi Technique
The Delphi technique is an iterative, anonymous forecasting and consensus-building method where experts provide estimates or opinions in multiple rounds, with summarized feedback between rounds.
Agile Estimation Techniques
Agile estimation techniques are lightweight methods used by agile teams to estimate the size, effort, or complexity of work items, including story points, planning poker, T-shirt sizing, and relative estimation.
Expert Judgment
Expert judgment is a technique that relies on the specialized knowledge and experience of individuals or groups with training, expertise, or skills in a specific area relevant to the activity being performed.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Matrix Diagrams
Matrix diagrams are a data representation technique that uses a grid format to show relationships between two or more groups of factors, commonly used for responsibility assignments and prioritization.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Part of
Tools & Techniques
Practice Wideband Delphi
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.