Skip to content
PMPCAPM

Wideband Delphi

Wideband Delphi is a consensus-based estimation technique that extends the Delphi method by adding team discussion between anonymous estimation rounds to improve estimate accuracy.

Share:

Explanation

Wideband Delphi is a variation of the traditional Delphi technique adapted for software and project estimation. Like the original Delphi, it uses multiple rounds of anonymous estimation. However, Wideband Delphi adds group discussion between rounds, allowing estimators to share their reasoning, ask clarifying questions, and understand different perspectives before re-estimating.

The process typically involves a moderator presenting the work item, the team independently recording their estimates, all estimates being revealed simultaneously, the team discussing the highest and lowest estimates to understand the reasoning, and then re-estimating. This cycle continues until the estimates converge within an acceptable range.

Planning poker, widely used in agile teams, is a direct descendant of Wideband Delphi. Both techniques combine the bias-reduction benefits of anonymous estimation with the information-sharing benefits of team discussion. Wideband Delphi produces more accurate estimates than either individual expert judgment or simple group averaging.

Key Points

  • Extends Delphi with team discussion between anonymous estimation rounds
  • Reduces bias while sharing information that improves accuracy
  • Planning poker is a popular variant used in agile
  • Produces more accurate estimates than individual judgment or simple averaging

Exam Tip

Wideband Delphi differs from classic Delphi by adding face-to-face discussion between rounds. Planning poker is essentially Wideband Delphi adapted for agile teams.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Matrix Diagrams

Matrix diagrams are a data representation technique that uses a grid format to show relationships between two or more groups of factors, commonly used for responsibility assignments and prioritization.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Part of

Tools & Techniques

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.