Project
Know it well enough for the exam? Questions on Project are scenario-based, not definitional.
Practice it freeExplanation
The defining characteristics of a project are its temporary nature and unique output. Temporary means every project has a definite beginning and end; the end is reached when the objectives have been achieved, when it becomes clear the objectives cannot be met, or when the need for the project no longer exists. Unique means the deliverable differs in some distinguishing way from all other products, services, or results.
Projects drive change in organizations. They move an organization from one state to another in order to achieve a specific objective, whether that is building a new software application, constructing a bridge, or implementing a new business process. Projects can exist at any level of the organization and can involve a single person or thousands.
It is important to distinguish projects from ongoing operational work. While operations are repetitive and sustain the business, projects are temporary and produce something new. Understanding this distinction is fundamental to applying the right management approach to each type of work.
Key Points
- •Temporary — has a definite start and finish
- •Creates a unique product, service, or result
- •Drives organizational change from a current state to a future state
- •Can be undertaken at any organizational level and vary greatly in size
Exam Tip
When the exam describes work that is temporary and produces something unique, it is a project — even if it sounds routine. Focus on the temporary and unique criteria.
Frequently Asked Questions
Related Topics
Program
A program is a group of related projects, subsidiary programs, and program activities managed in a coordinated manner to obtain benefits not available from managing them individually.
Portfolio
A portfolio is a collection of projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives.
Operations vs Projects
Operations are ongoing, repetitive activities that sustain an organization, while projects are temporary endeavors that create unique outputs.
Project Charter
A project charter is a document issued by the project sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Predictive Life Cycle (Waterfall)
A predictive life cycle is a plan-driven approach where the project scope, schedule, and cost are determined early and changes are carefully managed.
Subsidiary Plans
Subsidiary plans are the individual management plans that are components of the overall project management plan, each addressing a specific Knowledge Area or management function.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Part of
PM Fundamentals & Frameworks
Practice Project
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.