Process Groups
Foundational concept
Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.
Process Groups are a logical grouping of project management processes categorized into five groups: Initiating, Planning, Executing, Monitoring and Controlling, and Closing.
Know it well enough for the exam? Questions on Process Groups are scenario-based, not definitional.
Practice it freeExplanation
The five Process Groups provide a structured way to organize the 49 project management processes defined in the PMBOK Guide Sixth Edition. These groups are not phases of the project life cycle; rather, they are collections of processes that may be performed in any phase. In a multi-phase project, all five Process Groups may be repeated within each phase.
The Process Groups interact with each other throughout the project. The output of one process often becomes the input to another. For example, the project charter (an output of the Initiating Process Group) becomes an input to many Planning processes. The Monitoring and Controlling Process Group overlaps with all other groups because performance must be observed and measured throughout the project.
Understanding Process Groups is essential for both the PMP and CAPM exams. The CAPM exam in particular tests knowledge of which processes belong to which Process Groups and Knowledge Areas. The PMP exam focuses more on applying these processes in realistic scenarios, understanding their interactions, and knowing when to use which process.
Key Points
- •Five groups: Initiating, Planning, Executing, Monitoring and Controlling, Closing
- •Not project phases — they can occur in any phase of the project
- •Processes interact through inputs, tools and techniques, and outputs
- •Monitoring and Controlling spans the entire project
Exam Tip
Do not confuse Process Groups with project phases. A single phase can include activities from all five Process Groups. The exam frequently tests this distinction.
Frequently Asked Questions
Related Topics
Initiating Process Group
The Initiating Process Group consists of processes performed to define a new project or a new phase of an existing project by obtaining authorization to start.
Planning Process Group
The Planning Process Group consists of processes performed to establish the total scope of the effort, define objectives, and develop the course of action required to attain those objectives.
Executing Process Group
The Executing Process Group consists of processes performed to complete the work defined in the project management plan to satisfy project requirements.
Monitoring and Controlling Process Group
The Monitoring and Controlling Process Group consists of processes required to track, review, and regulate the progress and performance of the project, identify areas where changes to the plan are needed, and initiate corresponding changes.
Closing Process Group
The Closing Process Group consists of processes performed to formally complete or close the project, phase, or contract.
Knowledge Areas
Knowledge Areas are the ten identified areas of project management expertise defined in the PMBOK Guide, each encompassing a set of related processes.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Predictive Life Cycle (Waterfall)
A predictive life cycle is a plan-driven approach where the project scope, schedule, and cost are determined early and changes are carefully managed.
Subsidiary Plans
Subsidiary plans are the individual management plans that are components of the overall project management plan, each addressing a specific Knowledge Area or management function.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Part of
PM Fundamentals & Frameworks
Practice Process Groups
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.