Skip to content
PMPCAPM

Start-to-Finish (SF) Dependency

A Start-to-Finish (SF) dependency is a logical relationship in which a successor activity cannot finish until a predecessor activity has started.

Share:

Know it well enough for the exam? Questions on Start-to-Finish (SF) Dependency are scenario-based, not definitional.

Practice it free

Explanation

Start-to-Finish is the rarest and most counterintuitive of the four PDM dependency types. In an SF relationship, the start of the predecessor activity controls when the successor activity can finish. The successor may already be in progress, but it cannot be completed until the predecessor begins.

The classic example of an SF relationship is a shift changeover. The night shift (successor) cannot finish until the day shift (predecessor) starts. The night shift workers must remain on duty until the day shift workers arrive and begin their work. Another example is a legacy system that must remain operational (successor) until the new replacement system goes live (predecessor starts).

SF dependencies are seldom used in practice and rarely appear in project schedules. However, they are frequently tested on the PMP and CAPM exams because they are the most commonly confused relationship type. Understanding the direction of the dependency (the predecessor's start governs the successor's finish) is essential for exam success.

Key Points

  • •Rarest of the four PDM dependency types
  • •Successor cannot finish until predecessor starts
  • •Classic example: shift changeover or system cutover
  • •Frequently tested on PMP/CAPM exams despite rare practical use

Exam Tip

SF is the most commonly tested tricky dependency. Remember: the predecessor STARTING allows the successor to FINISH. Think of a guard who cannot leave until the replacement arrives.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Resource Smoothing

Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Part of

Schedule Management

Study full domain →

Practice Start-to-Finish (SF) Dependency

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.