Make-or-Buy Analysis
Make-or-buy analysis is a technique used to determine whether a particular product or service should be produced internally by the project team or purchased from an external source.
Know it well enough for the exam? Questions on Make-or-Buy Analysis are scenario-based, not definitional.
Practice it freeExplanation
Make-or-buy analysis compares the costs and benefits of producing a deliverable in-house versus acquiring it externally. Direct and indirect costs for both options are evaluated, including purchase price, management overhead, ongoing maintenance, and opportunity costs. The analysis also considers non-cost factors such as available capacity, expertise, schedule constraints, and strategic considerations.
For the "make" option, the organization retains full control over quality and intellectual property but bears all production risks and requires sufficient internal capability. For the "buy" option, the organization transfers some risk to the seller but introduces dependency on an external party and must invest in contract management.
This analysis is a key tool in Plan Procurement Management and directly influences procurement decisions. The results feed into the procurement management plan and may also affect the project scope baseline if work is outsourced.
Key Points
- •Compares total cost of internal production versus external purchase
- •Considers both financial and non-financial factors
- •A tool/technique of Plan Procurement Management
- •Results influence scope baseline and procurement management plan
Exam Tip
On the exam, make-or-buy analysis is a data analysis technique within Plan Procurement Management. Consider both direct costs (labor, materials) and indirect costs (management overhead, lost opportunity).
Frequently Asked Questions
Related Topics
Plan Procurement Management
Plan Procurement Management is the process of documenting project procurement decisions, specifying the approach, and identifying potential sellers.
Procurement Strategy
Procurement strategy defines the project delivery method, the type of legally binding agreement, and the approach for managing procurements throughout the project lifecycle.
Independent Estimates
Independent estimates are cost or price benchmarks developed by the buyer or a third party to serve as a check against seller-proposed pricing during procurement.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Stakeholder Mapping
Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.
Part of
Procurement Management
Practice Make-or-Buy Analysis
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.