Procurement Strategy
Procurement strategy defines the project delivery method, the type of legally binding agreement, and the approach for managing procurements throughout the project lifecycle.
Know it well enough for the exam? Questions on Procurement Strategy are scenario-based, not definitional.
Practice it freeExplanation
A procurement strategy addresses three key dimensions: the delivery method (such as design-bid-build, design-build, or turnkey), the contract payment type (fixed-price, cost-reimbursable, or time and materials), and the procurement phases (single-phase or multi-phase). The strategy is shaped by project risk, complexity, schedule urgency, and the competitive landscape.
Selecting the right procurement strategy is critical because it determines how risk is allocated between buyer and seller. For example, a fixed-price strategy shifts cost risk to the seller, while a cost-reimbursable strategy keeps cost risk with the buyer but provides more flexibility for poorly defined scope. The strategy also influences how many sellers are engaged and whether competition or sole-source selection is appropriate.
The procurement strategy is documented as part of the procurement management plan and guides all downstream procurement decisions, from writing the statement of work to selecting source evaluation criteria and negotiating contracts.
Key Points
- •Covers delivery method, contract payment type, and procurement phases
- •Determines risk allocation between buyer and seller
- •Influences the number of sellers and selection approach
- •Documented within the procurement management plan
Exam Tip
When an exam question asks about choosing a contract type or delivery method, think "procurement strategy." The right strategy depends on how well the scope is defined and where the risk should be allocated.
Frequently Asked Questions
Related Topics
Plan Procurement Management
Plan Procurement Management is the process of documenting project procurement decisions, specifying the approach, and identifying potential sellers.
Fixed-Price Contracts
Fixed-price contracts are a category of agreements where the seller is paid a set price for delivering a defined product or service, regardless of the seller's actual costs.
Cost-Reimbursable Contracts
Cost-reimbursable contracts are agreements where the buyer reimburses the seller for all legitimate actual costs incurred in performing the work, plus a fee representing the seller's profit.
Time and Materials (T&M) Contracts
A Time and Materials (T&M) contract is a hybrid agreement that combines elements of both fixed-price and cost-reimbursable contracts, paying the seller fixed rates per unit of time or materials with the total cost determined by actual quantities used.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Stakeholder Mapping
Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.
Part of
Procurement Management
Practice Procurement Strategy
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.