Skip to content
PMPCAPM

Procurement Strategy

Procurement strategy defines the project delivery method, the type of legally binding agreement, and the approach for managing procurements throughout the project lifecycle.

Share:

Know it well enough for the exam? Questions on Procurement Strategy are scenario-based, not definitional.

Practice it free

Explanation

A procurement strategy addresses three key dimensions: the delivery method (such as design-bid-build, design-build, or turnkey), the contract payment type (fixed-price, cost-reimbursable, or time and materials), and the procurement phases (single-phase or multi-phase). The strategy is shaped by project risk, complexity, schedule urgency, and the competitive landscape.

Selecting the right procurement strategy is critical because it determines how risk is allocated between buyer and seller. For example, a fixed-price strategy shifts cost risk to the seller, while a cost-reimbursable strategy keeps cost risk with the buyer but provides more flexibility for poorly defined scope. The strategy also influences how many sellers are engaged and whether competition or sole-source selection is appropriate.

The procurement strategy is documented as part of the procurement management plan and guides all downstream procurement decisions, from writing the statement of work to selecting source evaluation criteria and negotiating contracts.

Key Points

  • •Covers delivery method, contract payment type, and procurement phases
  • •Determines risk allocation between buyer and seller
  • •Influences the number of sellers and selection approach
  • •Documented within the procurement management plan

Exam Tip

When an exam question asks about choosing a contract type or delivery method, think "procurement strategy." The right strategy depends on how well the scope is defined and where the risk should be allocated.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Part of

Procurement Management

Study full domain →

Practice Procurement Strategy

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.