Fixed-Price Contracts
Fixed-price contracts are a category of agreements where the seller is paid a set price for delivering a defined product or service, regardless of the seller's actual costs.
Know it well enough for the exam? Questions on Fixed-Price Contracts are scenario-based, not definitional.
Practice it freeExplanation
Fixed-price contracts place the majority of cost risk on the seller. The seller agrees to deliver the specified scope for a predetermined price, so any cost overruns are absorbed by the seller and any savings are retained by the seller. This incentivizes the seller to control costs and work efficiently.
There are three main subtypes: Firm Fixed-Price (FFP), which has no price adjustments; Fixed-Price Incentive Fee (FPIF), which includes incentive adjustments based on performance; and Fixed-Price with Economic Price Adjustment (FPEPA), which allows price changes based on specific economic conditions over long contract periods.
Fixed-price contracts are most appropriate when the scope of work is well-defined and the risks are well-understood. They provide cost certainty for the buyer but require thorough requirements definition upfront. If the scope is unclear or likely to change significantly, a fixed-price contract can lead to disputes, excessive change orders, or seller financial distress.
Key Points
- •Seller bears the majority of cost risk
- •Best suited for well-defined scope with understood risks
- •Three subtypes: FFP, FPIF, and FPEPA
- •Provides cost predictability for the buyer
Exam Tip
Fixed-price contracts shift cost risk to the seller. They require well-defined scope. If the exam describes a project with clear specifications and a complete SOW, fixed-price is the likely answer.
Frequently Asked Questions
Related Topics
Firm Fixed-Price (FFP)
A Firm Fixed-Price (FFP) contract sets a fixed total price for a defined product or service, and the price does not change regardless of the seller's actual costs.
Fixed-Price Incentive Fee (FPIF)
A Fixed-Price Incentive Fee (FPIF) contract sets a target cost, target profit, ceiling price, and a share ratio that adjusts the seller's fee based on actual performance against the target cost.
Fixed-Price Economic Price Adjustment (FPEPA)
A Fixed-Price with Economic Price Adjustment (FPEPA) contract is a fixed-price agreement that includes a provision for predefined price adjustments tied to specific economic conditions such as inflation or commodity price changes.
Cost-Reimbursable Contracts
Cost-reimbursable contracts are agreements where the buyer reimburses the seller for all legitimate actual costs incurred in performing the work, plus a fee representing the seller's profit.
Procurement Strategy
Procurement strategy defines the project delivery method, the type of legally binding agreement, and the approach for managing procurements throughout the project lifecycle.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Stakeholder Mapping
Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.
Part of
Procurement Management
Practice Fixed-Price Contracts
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.