Skip to content
PMPCAPM

Cost-Reimbursable Contracts

Cost-reimbursable contracts are agreements where the buyer reimburses the seller for all legitimate actual costs incurred in performing the work, plus a fee representing the seller's profit.

Share:

Know it well enough for the exam? Questions on Cost-Reimbursable Contracts are scenario-based, not definitional.

Practice it free

Explanation

Cost-reimbursable contracts place the majority of cost risk on the buyer. The seller is paid for actual allowable costs plus an additional fee, so if costs increase, the buyer pays more. This contract type is appropriate when the scope of work cannot be precisely defined at the outset, such as in research and development, new technology projects, or situations with significant uncertainty.

The three main subtypes are Cost Plus Fixed Fee (CPFF), Cost Plus Incentive Fee (CPIF), and Cost Plus Award Fee (CPAF). Each differs in how the fee component is determined. All cost-reimbursable contracts require the buyer to have systems in place to monitor and audit the seller's costs.

Cost-reimbursable contracts provide maximum flexibility for scope changes and evolving requirements. However, they require more buyer oversight than fixed-price contracts because the buyer needs to verify that claimed costs are reasonable and allowable. The buyer should define allowable costs, audit requirements, and reporting standards in the contract.

Key Points

  • •Buyer bears the majority of cost risk
  • •Seller is reimbursed for actual costs plus a fee
  • •Three subtypes: CPFF, CPIF, and CPAF
  • •Best suited for undefined or evolving scope

Exam Tip

Cost-reimbursable contracts transfer cost risk to the buyer. They are used when scope is uncertain. The buyer must actively monitor seller costs. This is the opposite of fixed-price risk allocation.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Part of

Procurement Management

Study full domain →

Practice Cost-Reimbursable Contracts

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.