Earned Value Analysis
Earned value analysis (EVA) is a data analysis technique that integrates scope, schedule, and cost data to objectively measure project performance and progress against baselines.
Know it well enough for the exam? Questions on Earned Value Analysis are scenario-based, not definitional.
Practice it freeExplanation
Earned value analysis is one of the most powerful tools in the project manager's arsenal for measuring project performance. It compares three key values: Planned Value (PV), which represents the authorized budget for scheduled work; Earned Value (EV), which represents the value of work actually completed; and Actual Cost (AC), which represents the money actually spent on the work performed.
From these three values, EVA derives performance metrics including Schedule Variance (SV = EV - PV), Cost Variance (CV = EV - AC), Schedule Performance Index (SPI = EV / PV), and Cost Performance Index (CPI = EV / AC). These metrics enable objective assessment of whether the project is on schedule, within budget, or both. EVA also supports forecasting through Estimate at Completion (EAC) and Estimate to Complete (ETC) calculations.
EVA is most commonly used in the Control Costs and Control Schedule processes but requires proper baseline establishment during planning. It works best on projects where work can be measured in terms of completed deliverables or percentage complete.
Key Points
- •Integrates scope, schedule, and cost into unified performance measurement
- •Core values: PV (Planned Value), EV (Earned Value), AC (Actual Cost)
- •Derives SV, CV, SPI, CPI for performance assessment
- •Supports forecasting with EAC and ETC calculations
Exam Tip
EVA questions are common on both PMP and CAPM. Memorize all the formulas. CPI is the most critical metric because cost performance is hardest to recover once it deteriorates.
Frequently Asked Questions
Related Topics
Variance Analysis
Variance analysis is a data analysis technique that compares actual project performance to the planned baseline to determine the magnitude and cause of deviations.
Trend Analysis
Trend analysis is a data analysis technique that examines project performance data over time to identify patterns and forecast future performance or outcomes.
Cost-Benefit Analysis
Cost-benefit analysis is a data analysis technique that compares the expected costs of an action or decision against its anticipated benefits to determine its financial viability and value.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Matrix Diagrams
Matrix diagrams are a data representation technique that uses a grid format to show relationships between two or more groups of factors, commonly used for responsibility assignments and prioritization.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Part of
Tools & Techniques
Practice Earned Value Analysis
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.