Create WBS
Foundational concept
Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.
Create WBS is the process of subdividing project deliverables and project work into smaller, more manageable components.
Know it well enough for the exam? Questions on Create WBS are scenario-based, not definitional.
Practice it freeExplanation
Create WBS is the process that takes the project scope statement and requirements documentation and breaks them down into a hierarchical decomposition of the total scope of work. The resulting work breakdown structure organizes and defines the total scope of the project, with each descending level representing an increasingly detailed definition of the work.
The primary tool used is decomposition, which involves breaking deliverables into smaller pieces until the work is at a level where it can be reliably estimated, scheduled, monitored, and controlled. The lowest level of the WBS is called the work package. The team can use a top-down approach, an organization-specific guideline, or WBS templates from previous projects.
The outputs of Create WBS include the scope baseline (the approved scope statement, WBS, and WBS dictionary) and project documents updates. The scope baseline is a critical component of the project management plan and serves as the reference point against which all scope-related performance is measured.
Key Points
- •Subdivides deliverables and work into smaller, manageable components
- •Primary technique is decomposition
- •Lowest level of the WBS is the work package
- •Produces the scope baseline (scope statement + WBS + WBS dictionary)
Exam Tip
Create WBS is a Planning process. The scope baseline is established here, not during Define Scope. The scope baseline consists of three elements: the scope statement, the WBS, and the WBS dictionary.
Frequently Asked Questions
Related Topics
Work Breakdown Structure (WBS)
A work breakdown structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.
WBS Dictionary
The WBS dictionary is a document that provides detailed deliverable, activity, and scheduling information about each component in the work breakdown structure.
Decomposition
Decomposition is a technique used to divide and subdivide the project scope and deliverables into smaller, more manageable parts until the work is defined at the work package level.
Scope Baseline
The scope baseline is the approved version of the project scope statement, work breakdown structure (WBS), and its associated WBS dictionary, used as a reference for measuring project scope performance.
Work Package
A work package is the lowest level of the work breakdown structure, representing a deliverable or project work component that can be estimated, scheduled, monitored, and controlled.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Stakeholder Mapping
Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.
Part of
Scope Management
Practice Create WBS
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.