Skip to content
PMPCAPM

Work Package

A work package is the lowest level of the work breakdown structure, representing a deliverable or project work component that can be estimated, scheduled, monitored, and controlled.

Explanation

Work packages sit at the bottom of the WBS hierarchy and represent the smallest units of deliverable-oriented work that the project team defines during scope planning. They are the point at which cost and duration can be reliably estimated, work can be assigned to a responsible individual or team, and performance can be tracked.

During the Define Activities process in Schedule Management, work packages are further decomposed into activities (the actual tasks to be performed). This distinction is important: the WBS ends at the work package level, and activities are defined in the schedule, not in the WBS.

Work packages are typically described in detail in the WBS dictionary with attributes such as a code of account identifier, a statement of work, responsible organization, schedule milestones, acceptance criteria, and cost estimates. The size of a work package follows the general guideline of the 8/80 rule, meaning it should require between 8 and 80 hours of effort, though this is a guideline rather than a strict rule.

Key Points

  • Lowest level of the WBS hierarchy
  • Can be reliably estimated, scheduled, and controlled
  • Further decomposed into activities during Define Activities
  • Follows the 8/80 guideline (8 to 80 hours of effort)

Exam Tip

Activities are NOT part of the WBS. The WBS stops at the work package level. Activities are created from work packages during the Define Activities process in Schedule Management.

Frequently Asked Questions

Related Topics

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.