Skip to content
PMPCAPM

Alternatives Analysis

Alternatives analysis is a technique used to evaluate different approaches, methods, or options for accomplishing project work, helping the team select the best way to define and deliver the scope.

Share:

Know it well enough for the exam? Questions on Alternatives Analysis are scenario-based, not definitional.

Practice it free

Explanation

Alternatives analysis is a broadly applicable technique used across multiple knowledge areas and processes. In scope management, it is used during Define Scope and Collect Requirements to evaluate different ways to meet project requirements, deliver the product, or structure the project work. The goal is to identify the approach that best balances scope, cost, schedule, quality, risk, and resource constraints.

The technique involves identifying multiple feasible alternatives, evaluating each against defined criteria, and selecting the option that provides the most favorable outcome for the project. Evaluation criteria may include cost, time to implement, technical feasibility, risk level, resource availability, and alignment with organizational strategy.

Alternatives analysis is not unique to scope management. It appears in cost management (evaluating make-vs-buy decisions), schedule management (evaluating scheduling approaches), risk management (evaluating response strategies), and other areas. Understanding that it is a general-purpose analytical technique applied in many contexts is important for the exam.

Key Points

  • •Evaluates different approaches for accomplishing project work
  • •Used in Define Scope, Collect Requirements, and many other processes
  • •Considers cost, schedule, risk, feasibility, and other criteria
  • •General-purpose technique applied across multiple knowledge areas

Exam Tip

Alternatives analysis appears in many processes across the PMBOK Guide. On the exam, it is the answer when the question asks about evaluating different options or approaches to accomplish work.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Part of

Scope Management

Study full domain →

Practice Alternatives Analysis

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.