Skip to content
PMPCAPM

Sunk Costs

Sunk costs are expenditures that have already been incurred and cannot be recovered, regardless of future decisions or project outcomes.

Share:

Explanation

Sunk costs represent money, time, or resources that have been spent and cannot be reclaimed. The critical principle is that sunk costs should not influence future project decisions. Whether to continue, modify, or cancel a project should be based on future costs and benefits, not on how much has already been invested.

The sunk cost fallacy—sometimes called "throwing good money after bad"—occurs when decision-makers continue investing in a failing project because they have already spent so much. Rational decision-making requires ignoring sunk costs and evaluating the go-forward economics independently.

On the exam, sunk cost questions typically test whether you understand that past expenditures should not drive future decisions. If a question describes a project that has spent $2 million but now looks unprofitable, the $2 million is a sunk cost. The decision to continue should depend only on whether the remaining work will produce value exceeding its remaining cost.

Key Points

  • Money already spent that cannot be recovered
  • Should NOT influence future project decisions
  • The sunk cost fallacy leads to continued investment in failing projects
  • Rational decisions consider only future costs and benefits

Exam Tip

Sunk costs should never factor into the decision to continue or cancel a project. Always evaluate go-forward decisions based on future costs and expected benefits only.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Power/Influence Grid

The power/influence grid is a stakeholder classification model that groups stakeholders based on their level of authority (power) and their active involvement or ability to affect the project (influence).

Part of

Business Environment & Strategy

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.