Skip to content
PMPCAPM

Opportunity Cost

Opportunity cost is the value of the next best alternative that is forgone when a decision is made to pursue a particular project or course of action.

Share:

Know it well enough for the exam? Questions on Opportunity Cost are scenario-based, not definitional.

Practice it free

Explanation

Every time an organization selects one project, it implicitly rejects alternatives. The opportunity cost is the value of the best rejected alternative. If an organization chooses Project A (expected return $500,000) over Project B (expected return $400,000), the opportunity cost of choosing Project A is $400,000—the value they gave up.

Opportunity cost is a fundamental economic concept that helps decision-makers understand the true cost of their choices. It is not a cash expense that appears on financial statements; rather, it represents the potential benefit that could have been gained from a different allocation of resources.

On the exam, opportunity cost questions typically present two or more project options and ask you to identify the opportunity cost of selecting one. Remember: the opportunity cost is always the value of the option you did not choose—specifically the highest-value alternative forgone.

Key Points

  • •The value of the best alternative not chosen
  • •Not a cash expense but an economic concept
  • •Critical for informed project selection decisions
  • •Always equals the value of the next best alternative forgone

Exam Tip

Opportunity cost equals the value of the project NOT selected. If you choose a $1M NPV project over a $750K NPV project, the opportunity cost is $750K.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Part of

Business Environment & Strategy

Study full domain →

Practice Opportunity Cost

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.