Skip to content
PMPCAPM

Stakeholder Cube

The stakeholder cube is a three-dimensional model that extends two-dimensional stakeholder classification grids by adding a third dimension, allowing simultaneous analysis of three stakeholder attributes such as power, interest, and attitude.

Share:

Know it well enough for the exam? Questions on Stakeholder Cube are scenario-based, not definitional.

Practice it free

Explanation

The stakeholder cube takes the concept of two-dimensional grids like the power/interest grid and adds a third axis to provide richer classification. For example, a stakeholder cube might plot power on the x-axis, interest on the y-axis, and attitude (supportive vs. resistant) on the z-axis. This allows the project manager to see combinations that two-dimensional models cannot capture.

The cube is particularly useful on complex projects with many stakeholders where two-dimensional models produce overly simplistic groupings. For instance, a high-power/high-interest stakeholder who is supportive requires a very different strategy than a high-power/high-interest stakeholder who is resistant. The cube makes this distinction visible.

While the stakeholder cube provides more nuanced analysis, it is also more complex to create and interpret. It is most appropriate for large, complex projects with significant stakeholder challenges. For simpler projects, two-dimensional models are usually sufficient.

Key Points

  • •Three-dimensional extension of two-dimensional stakeholder grids
  • •Can combine any three attributes: power, interest, attitude, influence, impact, etc.
  • •Provides more nuanced classification than two-dimensional models
  • •Best suited for complex projects with many diverse stakeholders

Exam Tip

The stakeholder cube is less commonly tested than the power/interest grid, but know that it exists as a three-dimensional extension for more complex analysis scenarios.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Power/Influence Grid

The power/influence grid is a stakeholder classification model that groups stakeholders based on their level of authority (power) and their active involvement or ability to affect the project (influence).

Stakeholder Analysis

Stakeholder analysis is a technique for systematically gathering and analyzing quantitative and qualitative information to determine whose interests should be taken into account throughout the project.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Part of

Stakeholder Management

Study full domain →

Practice Stakeholder Cube

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.