Issue Log
An issue log is a project document used to record and monitor all issues — problems, gaps, inconsistencies, or conflicts — that arise during the project and require resolution.
Know it well enough for the exam? Questions on Issue Log are scenario-based, not definitional.
Practice it freeExplanation
The issue log is first created during the Direct and Manage Project Work process and is maintained throughout the project. An issue is a current problem or condition that may impact project objectives, as opposed to a risk, which is an uncertain future event. Issues require attention and resolution, and the issue log provides the structured tracking mechanism.
Each entry in the issue log typically includes a unique identifier, a description of the issue, the date identified, the person who raised it, the assigned owner, the priority, the target resolution date, the current status, and the resolution. Issues may be technical (a component does not meet specifications), organizational (resource conflicts), or interpersonal (stakeholder disagreements).
The project manager is responsible for monitoring the issue log and ensuring that issues are addressed in a timely manner. Unresolved issues can escalate and negatively impact the project. Some issues may lead to change requests if their resolution requires modifications to the project management plan or baselines. The issue log is an input to multiple processes, including Manage Stakeholder Engagement and Monitor and Control Project Work.
Key Points
- •Records current problems requiring resolution, not uncertain future events (those are risks)
- •Created during Direct and Manage Project Work and updated throughout the project
- •Includes ID, description, owner, priority, target date, status, and resolution
- •Unresolved issues may escalate into change requests or risks
Exam Tip
Issues are current problems; risks are uncertain future events. If the exam describes a problem that is happening now, it belongs in the issue log. If it might happen, it belongs in the risk register.
Frequently Asked Questions
Related Topics
Direct and Manage Project Work
Direct and Manage Project Work is the process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the project objectives.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Change Requests
A change request is a formal proposal to modify any document, deliverable, or baseline on a project. Change requests include corrective actions, preventive actions, defect repairs, and updates.
Assumption Log
An assumption log is a project document used to record all assumptions and constraints identified throughout the project lifecycle.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Change Control Board (CCB)
A Change Control Board (CCB) is a formally chartered group responsible for reviewing, evaluating, approving, deferring, or rejecting changes to the project, and for recording and communicating those decisions.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Part of
Integration Management
Practice Issue Log
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.