Decision Tree Analysis
Decision tree analysis is a diagramming and quantitative technique used to evaluate multiple decision alternatives, each with associated costs, probabilities, and outcomes, to select the option with the best expected monetary value.
Know it well enough for the exam? Questions on Decision Tree Analysis are scenario-based, not definitional.
Practice it freeExplanation
A decision tree is a branching diagram that models a sequence of decisions and chance events. Decision nodes (squares) represent choices the project manager can make. Chance nodes (circles) represent uncertain events with associated probabilities. Each path through the tree ends with a payoff or cost value.
To analyze a decision tree, you work backward from the end outcomes (right to left). At each chance node, you calculate the EMV by multiplying probabilities by payoff values and summing them. At each decision node, you select the alternative with the best (highest for gains, lowest for costs) EMV. This process is called "folding back" the tree.
Decision tree analysis is particularly useful when deciding between alternatives such as build vs. buy, different vendors, or whether to invest in risk mitigation. It makes the decision logic transparent and quantifies the trade-offs, making it easier to justify the chosen path to stakeholders.
Key Points
- •Uses decision nodes (squares) and chance nodes (circles) in a branching diagram
- •EMV is calculated at each chance node and the best option is selected at decision nodes
- •Analyzed by "folding back" from right to left
- •Useful for build-vs-buy, make-or-buy, and go/no-go decisions
Exam Tip
Decision tree questions on the exam require you to calculate EMV at each branch and select the path with the best overall value. Practice reading decision tree diagrams and folding back.
Frequently Asked Questions
Related Topics
Expected Monetary Value (EMV)
Expected monetary value (EMV) is a quantitative risk analysis technique that calculates the average outcome of a risk event by multiplying the probability of occurrence by the monetary impact. EMV for threats is negative; for opportunities, it is positive.
Perform Quantitative Risk Analysis
Perform Quantitative Risk Analysis is the process of numerically analyzing the combined effect of identified individual risks and other sources of uncertainty on overall project objectives.
Plan Risk Responses
Plan Risk Responses is the process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure and to treat individual project risks.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Transfer (Risk Strategy)
Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Part of
Risk Management
Practice Decision Tree Analysis
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.