Skip to content
PMPCAPM

Perform Quantitative Risk Analysis

Perform Quantitative Risk Analysis is the process of numerically analyzing the combined effect of identified individual risks and other sources of uncertainty on overall project objectives.

Explanation

Quantitative risk analysis goes beyond the subjective assessments of qualitative analysis by using numerical techniques to evaluate the aggregate effect of risks on cost, schedule, and other objectives. It produces probabilistic estimates such as the likelihood of meeting a target date or budget and the amount of contingency reserve needed.

Key techniques include Monte Carlo simulation, sensitivity analysis (tornado diagrams), expected monetary value (EMV) analysis, and decision tree analysis. These methods require quantitative data—probability distributions, three-point estimates, and historical data—making the process more resource-intensive than qualitative analysis.

Quantitative analysis is not performed on every project. It is most valuable on large, complex projects where the stakes are high and sufficient data is available. The results update the risk report with overall project risk exposure, S-curve graphs, tornado diagrams, and probabilistic forecasts that inform reserve decisions and stakeholder communication.

Key Points

  • Uses numerical techniques to assess combined risk effects on objectives
  • Key tools: Monte Carlo simulation, sensitivity analysis, EMV, decision trees
  • Produces probabilistic forecasts and contingency reserve estimates
  • Performed only on high-priority risks or complex projects with sufficient data

Exam Tip

Quantitative analysis is optional and follows qualitative analysis. It is the only risk process that is explicitly not required on every project per the PMBOK.

Frequently Asked Questions

Related Topics

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.