Skip to content
PMPCAPM

Cost Plus Fixed Fee (CPFF)

A Cost Plus Fixed Fee (CPFF) contract reimburses the seller for all allowable costs and pays a fixed fee (profit) that does not change regardless of actual costs.

Share:

Know it well enough for the exam? Questions on Cost Plus Fixed Fee (CPFF) are scenario-based, not definitional.

Practice it free

Explanation

In a CPFF contract, the seller receives reimbursement for all legitimate costs incurred in performing the work plus a predetermined fixed fee. The fee is calculated as a percentage of the estimated costs at contract signing and remains constant even if actual costs are higher or lower than estimated. The fee can only change if the scope of work is formally modified.

CPFF provides minimal incentive for the seller to control costs because the seller's profit (the fixed fee) does not decrease when costs increase. The seller receives the same fee whether the project costs $1 million or $2 million. However, the seller does not benefit from cost overruns either, since the fee is fixed.

CPFF is the most common type of cost-reimbursable contract. It is appropriate when the scope is uncertain and the buyer wants the seller to perform work on a best-effort basis without penalizing or rewarding cost performance. It is simpler to administer than CPIF or CPAF because there is no incentive calculation required.

Key Points

  • •Fee is fixed at contract signing and does not change with actual costs
  • •Seller has minimal incentive to control costs
  • •Most common cost-reimbursable contract type
  • •Fee only changes if scope is formally modified

Exam Tip

In CPFF, the fee is fixed but the total cost to the buyer is not. The seller has no cost reduction incentive. If the exam asks about a contract with no seller cost incentive, CPFF is the answer.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Part of

Procurement Management

Study full domain →

Practice Cost Plus Fixed Fee (CPFF)

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.