Skip to content
PMPCAPM

Cost Plus Fixed Fee (CPFF)

A Cost Plus Fixed Fee (CPFF) contract reimburses the seller for all allowable costs and pays a fixed fee (profit) that does not change regardless of actual costs.

Share:

Explanation

In a CPFF contract, the seller receives reimbursement for all legitimate costs incurred in performing the work plus a predetermined fixed fee. The fee is calculated as a percentage of the estimated costs at contract signing and remains constant even if actual costs are higher or lower than estimated. The fee can only change if the scope of work is formally modified.

CPFF provides minimal incentive for the seller to control costs because the seller's profit (the fixed fee) does not decrease when costs increase. The seller receives the same fee whether the project costs $1 million or $2 million. However, the seller does not benefit from cost overruns either, since the fee is fixed.

CPFF is the most common type of cost-reimbursable contract. It is appropriate when the scope is uncertain and the buyer wants the seller to perform work on a best-effort basis without penalizing or rewarding cost performance. It is simpler to administer than CPIF or CPAF because there is no incentive calculation required.

Key Points

  • Fee is fixed at contract signing and does not change with actual costs
  • Seller has minimal incentive to control costs
  • Most common cost-reimbursable contract type
  • Fee only changes if scope is formally modified

Exam Tip

In CPFF, the fee is fixed but the total cost to the buyer is not. The seller has no cost reduction incentive. If the exam asks about a contract with no seller cost incentive, CPFF is the answer.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Power/Influence Grid

The power/influence grid is a stakeholder classification model that groups stakeholders based on their level of authority (power) and their active involvement or ability to affect the project (influence).

Part of

Procurement Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.