Story Points
Story points are a unit of measure used in agile to estimate the overall effort, complexity, and uncertainty involved in completing a user story or product backlog item.
Know it well enough for the exam? Questions on Story Points are scenario-based, not definitional.
Practice it freeExplanation
Story points are a relative estimation technique used by agile teams to size product backlog items. Rather than estimating in hours or days, the team assigns story points that represent the relative effort compared to other items. For example, if a simple feature is assigned 2 story points, a feature that is roughly three times as complex might receive 5 or 8 points.
Many teams use the Fibonacci sequence (1, 2, 3, 5, 8, 13, 21) or similar scales for story point values, as the increasing gaps between numbers reflect the growing uncertainty in larger items. The estimation is typically done through planning poker, where each team member independently selects a value, all values are revealed simultaneously, and differences are discussed until consensus is reached.
The sum of story points completed per iteration is the team velocity. Velocity is used to forecast how much work the team can complete in future iterations and when the project or release might be finished. Story points are team-specific and should not be compared across teams, as each team calibrates its own scale based on their unique context, skills, and experience.
Key Points
- •Relative measure of effort, complexity, and uncertainty
- •Often uses Fibonacci sequence for values
- •Estimated through planning poker or similar techniques
- •Team velocity (points per iteration) is used for forecasting
Exam Tip
Story points measure relative effort, not absolute time. Velocity (story points per iteration) is used for forecasting. Never compare velocity between different teams.
Frequently Asked Questions
Related Topics
User Stories
A user story is a short, simple description of a feature or requirement written from the perspective of the end user, following the format: "As a [role], I want [goal], so that [benefit]."
Product Backlog
The product backlog is an ordered list of everything that is known to be needed in the product, serving as the single source of requirements and the primary artifact for managing scope in agile projects.
Definition of Done
The definition of done (DoD) is a shared understanding within the agile team of the criteria that must be met before a product backlog item or increment is considered complete and ready for release.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Stakeholder Mapping
Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.
Part of
Scope Management
Practice Story Points
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.