Compromising
Compromising (also called reconciling) is a conflict resolution technique where each party gives up something to reach a mutually acceptable solution, resulting in a lose-lose outcome.
Know it well enough for the exam? Questions on Compromising are scenario-based, not definitional.
Practice it freeExplanation
Compromising involves finding a middle ground where each party makes concessions. While it does not fully satisfy anyone, it provides a workable solution when collaborating is not possible or when a quick resolution is needed. Both parties accept a degree of dissatisfaction in exchange for resolving the conflict.\n\nThis technique is useful when the parties have relatively equal power, when a temporary solution is acceptable, when time pressure exists, or when the stakes are moderate. It is faster than collaborating and may be the best available option when a perfect solution is not achievable.\n\nPMI considers compromising a moderate approach — better than forcing or withdrawing, but less ideal than collaborating. The key drawback is that because no one fully gets what they want, the underlying issues may resurface later. It should be used judiciously when a full collaborative solution is impractical.
Key Points
- •Each party gives up something to reach agreement
- •Considered a lose-lose outcome by PMI
- •Faster than collaborating but less durable
- •Appropriate when parties have equal power and time is limited
Exam Tip
Compromising is a lose-lose because both sides sacrifice. It is better than forcing or withdrawing but worse than collaborating. Know when it is the most appropriate choice.
Frequently Asked Questions
Related Topics
Conflict Management
Conflict management is the practice of identifying and handling conflicts in a timely, constructive manner to minimize negative impacts and leverage disagreement for improved outcomes.
Collaborating/Problem Solving
Collaborating (also called problem solving or confronting) is a conflict resolution technique that incorporates multiple viewpoints to reach a consensus and commitment from all parties, resulting in a win-win outcome.
Smoothing/Accommodating
Smoothing (also called accommodating) is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference, often at the expense of one party who yields to maintain harmony.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Stakeholder Mapping
Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.
Part of
Resource Management
Practice Compromising
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.