Skip to content
PMPCAPM

Risk Management Plan

The risk management plan is a component of the project management plan that describes how risk management activities will be structured and performed. It is the output of the Plan Risk Management process.

Share:

Explanation

The risk management plan is a subsidiary plan within the overall project management plan. It does not contain identified risks or risk responses; instead, it provides the methodology, roles, responsibilities, budgeting, timing, risk categories, definitions of probability and impact levels, the probability and impact matrix, stakeholder tolerances, and reporting formats.

This plan ensures that the degree, type, and visibility of risk management are proportional to both the risks and the importance of the project to the organization. It aligns the risk approach with organizational policies and stakeholder expectations.

A well-crafted risk management plan increases the likelihood that subsequent risk processes—identification, analysis, response planning, and monitoring—are executed effectively and consistently. It serves as the rulebook for all risk-related decisions throughout the project.

Key Points

  • Subsidiary plan within the project management plan
  • Defines methodology, roles, budget, timing, and risk categories
  • Does not list individual risks—those go in the risk register
  • Includes probability and impact definitions and the P&I matrix template

Exam Tip

On the exam, if a question asks where probability and impact scales are defined, the answer is the risk management plan—not the risk register.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Transfer (Risk Strategy)

Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Part of

Risk Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.