Skip to content
PMPCAPM

Plan Risk Management

Foundational concept

Not named in the current ECO. Still worth knowing — it underpins the situational questions and PMI's own experience verification uses the process groups.

Plan Risk Management is the process of defining how to conduct risk management activities for a project. It produces the risk management plan, which guides all subsequent risk processes.

Share:

Know it well enough for the exam? Questions on Plan Risk Management are scenario-based, not definitional.

Practice it free

Explanation

Plan Risk Management is the first process in the Project Risk Management Knowledge Area. It establishes the framework and approach for identifying, analyzing, responding to, and monitoring risks throughout the project lifecycle. The process is performed early in project planning and may be revisited as the project evolves.

Key inputs include the project charter, project management plan (especially the schedule and cost management plans), stakeholder register, enterprise environmental factors, and organizational process assets. The primary tool is expert judgment, supplemented by data analysis and meetings with key stakeholders to tailor the risk approach.

The output is the risk management plan, which defines roles and responsibilities, budgeting for risk activities, timing and frequency of risk processes, risk categories, probability and impact definitions, the probability and impact matrix format, stakeholder risk tolerances, and reporting formats. This plan does not list individual risks—it describes how risk management will be performed.

Key Points

  • •First process in Project Risk Management; sets the overall risk approach
  • •Performed early in planning and revisited as needed
  • •Outputs the risk management plan, not individual risks
  • •Tailors risk activities to project size, complexity, and stakeholder risk appetite

Exam Tip

Remember that Plan Risk Management produces the risk management plan (how you will do risk management), not the risk register. Do not confuse this process with Identify Risks.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Transfer (Risk Strategy)

Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Part of

Risk Management

Study full domain →

Practice Plan Risk Management

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.