Probability and Impact Matrix
The probability and impact matrix is a grid that maps the probability of a risk occurring against its potential impact on project objectives, producing a risk score used to prioritize risks.
Know it well enough for the exam? Questions on Probability and Impact Matrix are scenario-based, not definitional.
Practice it freeExplanation
The probability and impact matrix (P&I matrix) is a key tool in qualitative risk analysis. It combines predefined probability ratings (e.g., 0.1, 0.3, 0.5, 0.7, 0.9) with impact ratings on a similar scale. The intersection of a risk's probability and impact values yields a risk score, which determines whether the risk is categorized as high, moderate, or low priority.
The matrix is defined in the risk management plan, including the scales, thresholds, and color-coding (often red/yellow/green). Separate matrices may be created for different project objectives such as cost, schedule, scope, and quality, since a risk might have high impact on schedule but low impact on cost.
Risks in the high-priority (red) zone receive immediate attention—detailed analysis, response strategies, and dedicated risk owners. Moderate (yellow) risks are monitored and may have contingency plans. Low (green) risks are placed on a watch list and reviewed periodically.
Key Points
- •Combines probability and impact ratings to produce a risk score
- •Defined in the risk management plan with scales and thresholds
- •Separate matrices may exist for cost, schedule, scope, and quality
- •Categorizes risks into high, moderate, and low priority zones
Exam Tip
Know how to calculate a risk score: Risk Score = Probability x Impact. A risk with P=0.7 and I=0.8 scores 0.56, which typically falls in the high-priority zone.
Frequently Asked Questions
Related Topics
Perform Qualitative Risk Analysis
Perform Qualitative Risk Analysis is the process of prioritizing individual project risks by assessing their probability of occurrence and impact on project objectives.
Risk Management Plan
The risk management plan is a component of the project management plan that describes how risk management activities will be structured and performed. It is the output of the Plan Risk Management process.
Risk Categorization
Risk categorization is the grouping of risks by their source, affected area, or other useful criteria to identify concentrations of risk exposure and common root causes.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Transfer (Risk Strategy)
Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Part of
Risk Management
Practice Probability and Impact Matrix
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.