Skip to content
PMPCAPM

Probability and Impact Matrix

The probability and impact matrix is a grid that maps the probability of a risk occurring against its potential impact on project objectives, producing a risk score used to prioritize risks.

Share:

Know it well enough for the exam? Questions on Probability and Impact Matrix are scenario-based, not definitional.

Practice it free

Explanation

The probability and impact matrix (P&I matrix) is a key tool in qualitative risk analysis. It combines predefined probability ratings (e.g., 0.1, 0.3, 0.5, 0.7, 0.9) with impact ratings on a similar scale. The intersection of a risk's probability and impact values yields a risk score, which determines whether the risk is categorized as high, moderate, or low priority.

The matrix is defined in the risk management plan, including the scales, thresholds, and color-coding (often red/yellow/green). Separate matrices may be created for different project objectives such as cost, schedule, scope, and quality, since a risk might have high impact on schedule but low impact on cost.

Risks in the high-priority (red) zone receive immediate attention—detailed analysis, response strategies, and dedicated risk owners. Moderate (yellow) risks are monitored and may have contingency plans. Low (green) risks are placed on a watch list and reviewed periodically.

Key Points

  • •Combines probability and impact ratings to produce a risk score
  • •Defined in the risk management plan with scales and thresholds
  • •Separate matrices may exist for cost, schedule, scope, and quality
  • •Categorizes risks into high, moderate, and low priority zones

Exam Tip

Know how to calculate a risk score: Risk Score = Probability x Impact. A risk with P=0.7 and I=0.8 scores 0.56, which typically falls in the high-priority zone.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Transfer (Risk Strategy)

Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Part of

Risk Management

Study full domain →

Practice Probability and Impact Matrix

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.