Skip to content
PMPCAPM

Monte Carlo Simulation

Monte Carlo simulation is a quantitative risk analysis technique that uses random sampling of probability distributions for cost and schedule estimates to model possible project outcomes and calculate the probability of achieving targets.

Share:

Know it well enough for the exam? Questions on Monte Carlo Simulation are scenario-based, not definitional.

Practice it free

Explanation

Monte Carlo simulation runs thousands of iterations of a project model, each time randomly selecting values from the probability distributions assigned to uncertain variables (activity durations, costs, etc.). The result is a probability distribution of possible project outcomes rather than a single deterministic estimate.

For schedule analysis, the simulation might show that there is a 50% probability of completing the project by June 30 and an 85% probability of completing by July 15. For cost analysis, it might reveal that a $2 million budget has only a 40% chance of being sufficient, while $2.3 million provides 90% confidence. These insights directly inform contingency reserve calculations.

The simulation requires three-point estimates (optimistic, most likely, pessimistic) or other probability distributions for each uncertain element. The output is typically displayed as an S-curve (cumulative probability distribution) or histogram. It is the most commonly used technique in Perform Quantitative Risk Analysis.

Key Points

  • •Runs thousands of iterations using random sampling from probability distributions
  • •Produces S-curves showing probability of meeting cost/schedule targets
  • •Requires three-point estimates or defined probability distributions
  • •Directly informs contingency reserve amounts

Exam Tip

Monte Carlo simulation answers "What is the probability of finishing by date X or within budget Y?" It does not identify individual risks—it models aggregate uncertainty.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Transfer (Risk Strategy)

Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Part of

Risk Management

Study full domain →

Practice Monte Carlo Simulation

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.