Skip to content
PMPCAPM

Monte Carlo Simulation

Monte Carlo simulation is a quantitative risk analysis technique that uses random sampling of probability distributions for cost and schedule estimates to model possible project outcomes and calculate the probability of achieving targets.

Share:

Explanation

Monte Carlo simulation runs thousands of iterations of a project model, each time randomly selecting values from the probability distributions assigned to uncertain variables (activity durations, costs, etc.). The result is a probability distribution of possible project outcomes rather than a single deterministic estimate.

For schedule analysis, the simulation might show that there is a 50% probability of completing the project by June 30 and an 85% probability of completing by July 15. For cost analysis, it might reveal that a $2 million budget has only a 40% chance of being sufficient, while $2.3 million provides 90% confidence. These insights directly inform contingency reserve calculations.

The simulation requires three-point estimates (optimistic, most likely, pessimistic) or other probability distributions for each uncertain element. The output is typically displayed as an S-curve (cumulative probability distribution) or histogram. It is the most commonly used technique in Perform Quantitative Risk Analysis.

Key Points

  • Runs thousands of iterations using random sampling from probability distributions
  • Produces S-curves showing probability of meeting cost/schedule targets
  • Requires three-point estimates or defined probability distributions
  • Directly informs contingency reserve amounts

Exam Tip

Monte Carlo simulation answers "What is the probability of finishing by date X or within budget Y?" It does not identify individual risks—it models aggregate uncertainty.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Transfer (Risk Strategy)

Transfer is a threat response strategy that shifts the negative impact and ownership of a threat to a third party. The risk is not eliminated but the responsibility for managing it moves to another entity.

Burndown Chart

A Burndown Chart is a graphical representation of work remaining versus time in a Sprint or release, showing whether the team is on track to complete the planned work.

Resource Leveling

Resource leveling is a resource optimization technique in which adjustments are made to the project schedule to keep resource usage at or below a defined limit, often resulting in a longer project duration.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Relative Estimation

Relative Estimation is an agile technique where work items are sized in comparison to each other rather than in absolute units like hours or days, providing faster and more accurate estimates.

Cost Performance Index (CPI)

Cost Performance Index (CPI) is an EVM efficiency metric that measures cost performance as the ratio of earned value to actual cost: CPI = EV / AC.

Schedule Performance Index (SPI)

Schedule Performance Index (SPI) is an EVM efficiency metric that measures schedule performance as the ratio of earned value to planned value: SPI = EV / PV.

Earned Value Management (EVM)

Earned Value Management (EVM) is a methodology that integrates scope, schedule, and cost data to assess project performance and progress objectively.

Part of

Risk Management

Study full domain →

Test your knowledge

Practice scenario-based questions on this topic with detailed explanations.