Gantt Chart
A Gantt chart is a bar chart that presents schedule information with activities listed on the vertical axis, dates shown on the horizontal axis, and activity durations shown as horizontal bars placed according to start and finish dates.
Know it well enough for the exam? Questions on Gantt Chart are scenario-based, not definitional.
Practice it freeExplanation
The Gantt chart, also known as a bar chart, is the most widely used format for presenting and communicating the project schedule. Named after Henry Gantt, who popularized it in the early 20th century, the chart provides a visual representation of when activities start, how long they last, and when they finish. The horizontal axis represents the project timeline, and each activity is shown as a bar spanning from its start date to its finish date.
Modern Gantt charts often include additional information such as dependency relationships (shown as arrows between bars), milestones (shown as diamonds or special symbols), the critical path (highlighted in a different color), progress indicators (showing percentage complete), and the schedule baseline (shown as a secondary bar for comparison). This makes them powerful tools for schedule communication and tracking.
Gantt charts are particularly useful for stakeholder communication because they are intuitive and easy to understand, even for people without project management expertise. However, for very large projects with hundreds or thousands of activities, Gantt charts can become unwieldy. In such cases, summary-level Gantt charts showing work packages or phases rather than individual activities may be more appropriate.
Key Points
- •Bar chart with activities on the vertical axis and time on the horizontal axis
- •Most widely used schedule presentation format
- •Can show dependencies, milestones, critical path, and progress
- •Intuitive for stakeholder communication
Exam Tip
Gantt charts are sometimes called bar charts on the exam. They show schedule information visually but are most useful for communication, not for calculating the critical path (use the network diagram for that).
Frequently Asked Questions
Related Topics
Milestone Chart
A milestone chart is a schedule presentation that identifies only the start or completion of major deliverables and key external interfaces, displaying milestones on a timeline.
Schedule Baseline
The schedule baseline is the approved version of the schedule model that is used as a basis for comparison with actual results to determine if corrective or preventive action is needed.
Develop Schedule
Develop Schedule is the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model for project execution, monitoring, and controlling.
Critical Path
The critical path is the longest sequence of activities in a project schedule network diagram that determines the shortest possible project duration.
Most-studied PMP concepts
High-yield topics our learners drill most before exam day.
Resource Leveling
Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.
Critical Path Method (CPM)
The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.
Resource Smoothing
Resource smoothing is a resource optimization technique that adjusts activities within their available float so that resource requirements do not exceed predefined limits, without changing the project end date.
Burndown Chart
A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.
Burn-Up Chart
A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.
Deliverables
A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.
Power Interest Grid (Power/Influence Grid)
The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.
Weighted Shortest Job First (WSJF)
Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.
Risk Register
The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.
Part of
Schedule Management
Practice Gantt Chart
Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.