Skip to content
PMPCAPM

Control Charts

A control chart is a graph used to study how a process changes over time, displaying data points plotted against upper and lower control limits to determine whether the process is in statistical control.

Share:

Know it well enough for the exam? Questions on Control Charts are scenario-based, not definitional.

Practice it free

Explanation

Control charts are one of the seven basic quality tools and are essential for monitoring process stability in the Control Quality process. A control chart has a center line representing the process mean, an upper control limit (UCL), and a lower control limit (LCL). These limits are typically set at three standard deviations (3 sigma) from the mean. Data points that fall within the control limits indicate the process is stable and in control.\n\nA process is considered out of control when data points fall outside the control limits or when non-random patterns appear in the data, such as the Rule of Seven (seven consecutive points on one side of the mean). When a process is out of control, it requires investigation and corrective action. It is important to distinguish between control limits (which represent the natural variation of the process) and specification limits (which represent the customer's quality requirements).\n\nControl charts help the project team distinguish between common cause variation (inherent to the process) and special cause variation (caused by unusual circumstances). Common cause variation is normal and expected; special cause variation signals a problem that needs attention. This distinction is critical for making appropriate quality management decisions.

Key Points

  • •One of the seven basic quality tools
  • •Uses upper control limit (UCL) and lower control limit (LCL), typically at 3 sigma
  • •Rule of Seven: seven consecutive points on one side of the mean indicates out of control
  • •Distinguishes common cause variation from special cause variation

Exam Tip

Know the Rule of Seven and the difference between control limits (process variation) and specification limits (customer requirements). A process can be in control but still not meet specifications.

Frequently Asked Questions

Related Topics

High-yield topics our learners drill most before exam day.

Burndown Chart

A burndown chart plots the work remaining (usually in story points) against time in a sprint or release, alongside an ideal line to zero, so the team can see each day whether it is on track to finish.

Burn-Up Chart

A burn-up chart plots completed work rising over time against a separate total-scope line, so progress and scope changes are visible independently; the work is finished when the two lines meet.

Resource Leveling

Resource leveling is a resource optimization technique that adjusts activity start and finish dates so that demand for a resource never exceeds its availability, accepting a longer schedule and a changed critical path if necessary.

Deliverables

A deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project, such as a software release, an audit report, or a trained support team.

Power Interest Grid (Power/Influence Grid)

The power interest grid is a 2x2 stakeholder mapping tool that plots each stakeholder by power (ability to affect the project) and interest (concern about its outcome) to decide how to engage them: manage closely, keep satisfied, keep informed, or monitor.

Critical Path Method (CPM)

The Critical Path Method (CPM) is a schedule network analysis technique that calculates early and late start and finish dates for every activity to find the longest path through the project, the minimum project duration, and the float on every other path.

Weighted Shortest Job First (WSJF)

Weighted Shortest Job First (WSJF) is a prioritization model, popularized by SAFe, that ranks work by cost of delay divided by job duration (usually estimated as job size), so the items that lose the most value per unit of time spent waiting are done first.

Risk Register

The risk register is a project document that records the details of individual project risks, including their identification, analysis results, response plans, and current status.

Stakeholder Mapping

Stakeholder mapping is the visual representation of stakeholder relationships, influence, interest, or other attributes using grids, matrices, or diagrams to support analysis and engagement planning.

Part of

Quality Management

Study full domain →

Practice Control Charts

Scenario-based questions with a full explanation on every answer — including why the distractors are wrong.